Live Demo — Real Active Project · Figures Rounded · Names & Companies Anonymized
Master Project Tracker Live Demo — Anonymized
OAC #6 — June 3, 2026  ·  Next OAC: June 10, 2026 at 11:00 AM
Contract Sum
$19.3M
Total GC contract value
Completion
65%
Of total scope, as of OAC #5
Current Pay App
#18 — May 19, 2026
Most recent draw application
Current Draw
$485K
This pay-app period
Balance to Complete
~$7.0M
Remaining contract value
Owner Target
Feb 28, 2027
Substantial completion goal

⚠ Critical Items — OAC #6 — June 3, 2026

Veneer approval — Owner Rep
TIME CRITICAL — must approve before June 15 Millwork Co. 2F delivery. His+hers vanity, massage vanity, cabana boxes pending.
Spiral stair slab / trench repair
URGENT — repair near stair trench must go through B&I. Speaker 6 to follow up with B&I contact.
Chandelier location — her master closet
Interiors Co. to provide dimensions. Painting on HOLD until resolved. Coordinate Interiors Co. + Interiors Lead.
Back deck / fire pit — scope
Scope package sent 6/2. Schedule walkthrough. Fire pit can start. Price concrete pour vs PT wood.
Roof HVAC isolators — city permit
Submitted to city; approval expected week of 6/8. Then schedule isolator install + final roofing coat.
Schedule variance: GC schedule Aug–Dec 2027 (5–10 month gap — unresolved)

This dashboard is the live operating picture for Miami Beach Flagship — the same tracker used by the contractor's PM, the site superintendent, and the owner's representative to run the project. It consolidates the OAC meeting record, the critical-task register, the city inspection log, owner decisions, subcontractor buyout, the field control board, and the master schedule into one view. Use the tabs above to move between them; the search box filters the active tab.

Critical Task Register

# Category Task Owner Status Due Source Notes
1.0 ✅ RESOLVED Gas revision — MEP Eng email approved 5/6, hard copies to follow MEP Eng ✅ APPROVED 5/6 5/6/2026 OAC2 CRITICAL MILESTONE. Gas revision was the master blocker. Walls can now proceed to close on 2nd floor. 2 signed/sealed hard copies still needed for city submission.
2.0 ✅ RESOLVED HVAC pre-drywall walk — completed 5/6 with HVAC Lead APM/Site Super ✅ DONE 5/6 5/6/2026 Task List + OAC2 Walk complete. New punch list from walkthrough: bed 1 drain, access panels, VIP filter slot, bed 2 damper filter racks. Site Super working remaining items.
3.0 ✅ RESOLVED Framing inspection — passed (except staff/service wing) Site Super ✅ PASSED (partial) Prior Inspections sheet Passed except Staff Area/Service Wing. Service wing needs correction.
4.0 ✅ RESOLVED City inspector — met, EOR engineer letter in progress Site Super/APM ✅ MET 5/4/2026 Task List Met with inspector. Recall inspection of front stairs + at-grade landing slab needed. Site Super getting EOR structural engineer letter.
5.0 ✅ RESOLVED Condensate lines — horizontal insulation materials arrived 5/1 Site Super/HVAC Lead ✅ Materials on site 5/1/2026 Task List Materials arrived 5/1. Site Super making HVAC Lead insulate horizontal condensate lines.
6.0 ✅ RESOLVED Remote AC sensors — locations given to HVAC Lead at 5/6 walkthrough APM/Site Super ✅ DONE 5/6/2026 Task List Locations given to HVAC Lead at walkthrough. HVAC Lead will install.
7.0 ✅ RESOLVED All fresh air dampers — HVAC Lead confirmed installed and working 5/6 HVAC Lead ✅ CONFIRMED 5/6/2026 Task List Confirmed with HVAC Lead at walkthrough.
8.0 ✅ RESOLVED Lighting Designer — exterior sconce locations marked outside massage balcony APM/Site Super ✅ DONE (low one pending) 5/6/2026 Task List Done except low one on side of walkway.
9.0 ✅ RESOLVED Return for guest bed 1 from corridor — the PE approved, in progress Site Super ✅ In Progress ASAP Task List the PE approved. Site Super in progress. Also needs to draw from hallway plenum per the engineer.
10.0 🔴 CRITICAL Wellness Center HVAC — upsize to 3 ton, new condenser (DECIDE 5/13) APM/MEP Eng Open — Awaiting Calcs 5/13/2026 OAC2 Existing 1.5 ton vs ~33K BTU load. New condenser + MEP revision required. the PE + MEP consultant running calculations. Keep ceiling open.
11.0 🔴 CRITICAL Gas revision hard copies — 2 signed/sealed to city MEP Eng Open ASAP OAC2 Email approved 5/6. City still needs 2 signed and sealed hard copies submitted.
12.0 🔴 CRITICAL Roof HVAC isolators — Mech Eng draft → HVAC Lead review → EOR stamp → city PM/APM In Progress ASAP OAC2 PM reviewing draft with HVAC Lead. Then EOR stamp. Then process with city.
13.0 🔴 CRITICAL His & Hers stone — GC needs area list for shop drawings PM Open ASAP Task List GC wants list of which bathrooms get stone first to start shop drawings. PM to make 2nd floor slab area list and email GC + APM.
14.0 🔴 CRITICAL Interior painting — pricing proposal under review (Owner Rep confirmed) APM/PM Open — Action Required ASAP OAC2 + Owner Rep 5/4 Leveling doc to ownership this week. Painting Sub ~$10K cheaper, fewer COs. If declined: remove closets or third bid.
15.0 🔴 CRITICAL Front stairs — recall inspection, EOR engineer letter Site Super Open ASAP Task List City inspector needs evidence. Site Super getting EOR structural engineer letter.
16.0 🔴 CRITICAL Floor boxes — eliminate wellness boxes pending MEP revision APM/PM Partial Approval ASAP OAC2 5/6 Approved by Owner Rep except wellness room. Cannot finalize until wellness MEP revision done.
17.0 🔴 CRITICAL Wellness center MEP revision (240V? No hyperbaric?) MEP Eng/the PE Open 5/13/2026 OAC1 + OAC2 MEP revision required for wellness room electrical. MEP Eng following up with the PE. MEP consultant comments 5/6.
18.0 🔴 CRITICAL HVAC HVAC Lead punch list from 5/6 walk — 4 items HVAC Lead/Site Super Open 5/13/2026 Task List walkthrough results 1) Bed 1 drain blocking filter 2) Relocate access panels bed 1 & 3 3) VIP suite filter slot (Fab Lead) 4) Bed 2 damper blocking filter racks — Fab Lead to change all ceiling AHU filter racks.
19.0 🔴 CRITICAL Bed 3 service wing framing — failed inspection, correction needed Site Super Open ASAP Inspections sheet Framing inspection passed except staff/service wing. Correct and recall.
20.0 🔴 CRITICAL Plumbing sub — formal notice still required APM/PM Open ASAP Site Super control board Pattern documented. Escalation path under review.
21.0 🟠 HIGH Carousel mock-up — 5/7 at 2pm (Fab Lead bending metal bar) APM/Fab Lead/Interiors Lead Scheduled 5/7/2026 OAC2 Brass inlay edge detail + deflection assessment with black tile. Interiors Lead reviewing. Written confirmation of pricing + credit needed.
22.0 🟠 HIGH 2nd floor soffit alignment issues — site walk 5/7 Site Super/APM Scheduled 5/7/2026 OAC2 Owner videos flagged misalignments. Resolve during site walk. Document corrective actions.
23.0 🟠 HIGH Facade Lead on site 5/7 to discuss facade metals with Site Super MEP Eng/Site Super Scheduled 5/7/2026 OAC2 Brake metal: MEP Eng sent marked-up shop drawings 5/6 evening. Fab Lead to site measure + samples. Owner Rep color approval needed.
24.0 🟠 HIGH Landscape — Landscape Arch on site 5/7, 2 signed/sealed copies for city APM Scheduled 5/7/2026 OAC2 Landscape Arch bringing plans for city processing.
25.0 🟠 HIGH Metal fencing — hidden areas to pickets, decorative at visible, add screens APM/Fab Lead Open 5/13/2026 OAC2 Marked drawings needed: decorative vs picket by location. Also add privacy screens for garage electrical panels + exterior water heaters + Jandy panels.
26.0 🟠 HIGH Civil engineer — Site Super sketch to reduce fees Site Super/APM In Progress 5/13/2026 OAC2 APM spoke to Civil Eng. Site Super sending sketch to reduce scope/fees.
27.0 🟠 HIGH Safe room doors — written quote, pick certified installer PM Open ASAP OAC1 + OAC2 Will come back with quotes per OAC2. Must pick installer before safe room door supplier can make shop drawings.
28.0 🟠 HIGH Millwork Co. — phased delivery discussion, Owner Rep watching PM Open ASAP Task List Owner Rep asking for delivery target date. PM to contact the Millwork Co. rep about phased delivery.
29.0 🟠 HIGH Tub filler + drain — her master bath, core drill + rough Site Super/Plumber Open ASAP Task List Site Super to core drill. Plumber installs rough in floor.
30.0 🟠 HIGH Anti-scalding valve — her master bath (inspector requires) PM/Plumber Open ASAP Task List PM sending detail. Plumber will find spot after rough is in floor.
31.0 🟠 HIGH Freon lines master mech closet — lower (told HVAC Lead at 5/6 walk) HVAC Lead/Site Super Open ASAP Task List Told HVAC Lead at walkthrough. Follow up to confirm.
32.0 🟠 HIGH Seal access panel back of elevator shaft Site Super Open ASAP Task List Site Super ordering panel that seals/locks. Confirm lock with PM before ordering.
33.0 🟠 HIGH Lighting Designer — 1st floor walk scheduled 5/20 APM/Site Super Scheduled 5/20/2026 Task List After Lighting Designer completes 2nd floor. Site Super meets Lighting Designer for 1st floor schedule.
34.0 🟠 HIGH HVAC Lead — 1st floor HVAC walk scheduled 5/20 APM/Site Super Scheduled 5/20/2026 Task List Coordinate with 1st floor electrical walk.
35.0 🟠 HIGH Stair ceiling mirror — rosette detail, drawings from the Architect in Procore MEP Eng/APM Open 5/13/2026 OAC2 Wood rosette to conceal chandelier lift. Millworker wood frame + separate mirror vendor. Latest drawings from the Architect in Procore.
36.0 🟠 HIGH NWF — gym floor proposal owed PM Open ASAP Task List NWF owes gym floor proposal. PM to follow up.
37.0 🟠 HIGH File front door — Cladding Vendor to provide NOA PM Open ASAP Task List NOA needed for permit.
38.0 🟠 HIGH File garage door — NOA from the door vendor, then complete inspection PM Open ASAP Task List Get NOA then finish inspection.
39.0 🟠 HIGH Shearwall — pedestals shop drawing for exterior wood deck PM/APM In Progress ASAP Task List Comments sent 5/1. Shop drawing needed for pedestals.
40.0 📅 SCHEDULE New schedule — after 2F drywall + stone coordination APM/Site Super/PM Open After drywall progress OAC2 5/6 APM/Site Super/PM to build new schedule after completing 2F drywall and coordinating flooring install on 2F.
41.0 📅 SCHEDULE Next OAC — 5/13/2026 at 12:00 PM or 12:30 PM All Scheduled 5/13/2026 OAC2 Proposed time change from 1:30pm to noon or 12:30.
NEW 🟠 HIGH Camera payment — responsibility clarified (GC) APM Open ASAP Site Super control board / CM Camera scope and payment responsibility clarified — sits with the GC.
NEW 🟠 HIGH Pool equipment payment — through GC accounting APM / GC accounting Open ASAP CM update 5/6 Pool contractor approved. All equipment payments to be processed through GC accounting (GC accounting). Not a CM action item.
NEW 🟠 HIGH Epoxy coating samples — acquire and have on site for owner review APM Open 5/13/2026 OAC 5/6 + CM update Engage epoxy vendor or specialist. Obtain epoxy floor coating samples for garage. Owner must review samples on site before decision. Coordinate with Interiors Co. walkthrough on garage cabinetry.
NEW 🟠 HIGH Jib doors for AC mech closets — APM to review Door Vendor product + pricing APM Open 5/13/2026 CM update 5/6 Two jib doors: one inside chef's kitchen AC mech closet, one just outside. These are BASIC (non-custom) doors now in the drywall scope — NOT Millwork Co. millwork. PM priced from Door Vendor. APM to review Door Vendor product and pricing.
NEW 🟠 HIGH AV Room HVAC — clarify exact equipment needed APM Open 5/13/2026 CM update 5/6 APM to determine exact equipment spec for AV room HVAC. Not a CM item. Include in APM's tracker.
NEW 🟠 HIGH Millwork Co. installer — APM + Site Super + Owner Rep to decide on site APM / Site Super / Owner Rep Open Next joint site visit CM update 5/6 APM and Site Super to discuss with Owner Rep directly next time all three are on site. Decision: current installer candidate vs. GC sourcing another. Must be agreed in person — not via email or OAC.
NEW 🟠 HIGH Garage cabinetry decision — cover in Interiors Co. walkthrough Interiors Co. / PM / APM Open Next Interiors Co. visit OAC 5/6 + CM update Determine in Interiors Co. walkthrough whether any garage cabinetry design is needed. Separately: Epoxy vendor samples must be on site for owner review. Both items to be addressed together.
NEW 📋 INFO AGG Glass Contractors — gym glass wall shop drawings in progress CM / AGG Glass In Progress Post-drywall inspection CM update 5/6 AGG Glass Contractors (Owner's contractor) handling gym glass wall. Initial shop drawings underway. Final measurements require finished wall, ceiling, and floor. Then fabrication. GC to ensure room completion is sequenced accordingly.
NEW 📋 INFO Shower enclosures / ribbed glass / mirrors — Glass Vendor + PM + APM APM / PM Open TBD CM update 5/6 CM has no role. Assign to APM and PM. RFPs sent to three fabricators. GC to manage selection process.
5/13 ✅ RESOLVED Interior priming — APPROVED to start week of May 18 APM / PM ✅ APPROVED 5/13 5/18/2026 OAC3 5/13 Decision made at OAC3. Painter to mobilize week of May 18.
5/13 ✅ RESOLVED Propane tank anti-flotation drawings — Mech Eng completed MEP Eng ✅ DRAWINGS COMPLETE 5/13/2026 OAC3 5/13 Stamped drawings ready. Now needs to be processed with city.
5/13 ✅ RESOLVED Main house transformer reorientation — REJECTED ✅ CLOSED 5/13/2026 OAC3 5/13 Too costly + FPL 8-foot clearance required. Orientation stays as-is.
5/13 🔴 CRITICAL Cryotherapy chamber — 230V vs 208V conflict, transformer noise, heat load APM / the PE Open — Researching Alt. 5/20/2026 OAC3 5/13 Cryofast unit requires 230V, house provides 208V. Noisy transformer required. 2-5kW heat load. Research 208V American units and split-unit options. Send Owner Rep specs.
5/13 🔴 CRITICAL Deck & fire pit substructure — Struct Eng engineered drawings URGENT Struct Eng Open — Crew Waiting ASAP OAC3 5/13 Pedestals have no NOA. New plan: PT wood substructure by Struct Eng. Drawings are priority — crew will stop without them.
5/13 🔴 CRITICAL Drywall screw inspection — pass by end of week 5/11 Site Super In Progress 5/14/2026 OAC3 5/13 Plumbers on site May 14 to complete so ceilings can close.
5/13 🔴 CRITICAL Facade/brake metal — color decision needed to proceed MEP Eng / Fab Lead Open — Color TBD 5/20/2026 OAC3 5/13 Fab Lead's engineer reviewing fastening details. Color must be decided before shop drawings can be finalized.
5/13 🟠 HIGH City handrails — front steps + fire pit steps (new requirement) MEP Eng Open 5/20/2026 OAC3 5/13 City courtesy walk resulted in minor handrail additions required. MEP Eng to incorporate into fencing revision.
5/13 🟠 HIGH Roof fencing VE — white/less expensive alternative MEP Eng / Fab Lead In Progress 5/20/2026 OAC3 5/13 AOR opposed black fencing on white roof. Owner Rep concerned about appearance. Explore less expensive white solution. MEP Eng to get VE marked-up drawings from Fab Lead.
5/13 🟠 HIGH Landscape tree locations — conflict with underground utilities APM / Landscape Arch Open 5/20/2026 OAC3 5/13 Trees on landscape plan conflict with underground utilities. Site walk needed with landscape architect.
5/13 🟠 HIGH Tile sub installer on site May 14 + Tile Lead starts May 15 Site Super / APM Scheduled 5/14–5/15 OAC3 5/13 Exterior stone installer kickoff also May 15. Pool contractor job walk May 15.
5/13 🟠 HIGH Carousel — negotiate price + Tile Sub installation method meeting May 14 APM / PM In Progress 5/14/2026 OAC3 5/13 Brass inlays expected May 14. Meet Tile Sub to approve installation method.
5/13 🟠 HIGH Noisy transformer — find insulated location, get specs from Lighting Designer APM / Lighting Designer Open 5/20/2026 OAC3 5/13 Possible cryo unit transformer described as 'jet engine' loud. Must find new location.
5/13 🟠 HIGH Interiors Co. — master carpet selection + bathroom 2 digital slab layout Interiors Lead / Interiors Co. Open 5/20/2026 OAC3 5/13 Interiors Lead to push Interiors Co.. Owner Rep to be involved in carpet selection.
5/13 🟠 HIGH Electrician proposal for step-up transformer — get and review with Owner Rep APM Open 5/20/2026 OAC3 5/13 Obtain electrician's proposal for transformer. Share with Owner Rep for decision.
5/13 📅 SCHEDULE Next OAC — May 20, 2026 at 12:00 PM All Scheduled 5/20/2026 OAC3 5/13 Week of May 25 to be scheduled earlier for Owner Rep.
5/18 ✅ RESOLVED Drywall screw inspection — 2ND FLOOR PASSED 5/18/2026 Site Super / Door Vendor Drywall ✅ PASSED 5/18 5/18/2026 Daily Log 5/18 CRITICAL MILESTONE. Entire 2nd floor passed. Door Vendor adding 10 finishers 5/19. 1F drywall starts 5/19. Backing installation begins 1F.
5/18 🔴 CRITICAL Plumbing sub — ABSENT 6 CONSECUTIVE DAYS (5/11–5/18). Formal notice NOW. APM / PM Open — Formal Notice Required IMMEDIATE Manpower Log 5/18 Zero presence 5/11 through 5/18. Door Vendor starts 1F tomorrow. Condensate drains and tub/shower roughs must be done before ceilings close or they get drywalled in permanently.
5/18 🔴 CRITICAL HVAC sub — absent 5/13–5/18. HVAC punch items must clear before 1F ceiling closure. APM / HVAC Lead Open — Escalate IMMEDIATE Manpower Log 5/18 6 consecutive absences. HVAC punch list from 5/6 walk still open. Must clear before 1F ceilings close — bed 1 drain, access panels, VIP filter slot, bed 2 damper racks.
5/27 🔴 CRITICAL Veneer approval — TIME CRITICAL before June 15 Millwork Co. 2F Interiors Lead / Owner Rep / Interiors Co. Open — URGENT BEFORE 6/15 OAC5 Must approve: her closet, his & her vanities, massage vanity, cabana bar. June 15 is hard deadline.
5/27 🔴 CRITICAL Gas Rough Inspection — TODAY 5/27. Pass = call 1F Framing Site Super / MEP Eng Inspection Today 5/27/2026 OAC5 If gas passes today, call 1F framing inspection immediately.
5/27 🔴 CRITICAL Back deck structural / shearwall (Struct Eng) — under review APM / Struct Eng / GC Open — Under review This week OAC5 Drawing interpretation vs. cost responsibility under review. Struct Eng coming this week.
5/27 🔴 CRITICAL FPL Easement — retrieve, notarize, submit Miami-Dade CM Open ASAP OAC5 Covenant from neighboring property. Must retrieve → notarize → submit to county before FPL relocates transformers.
5/27 🟠 HIGH Interior louvers — bottom detail unresolved Facade Lead / Fab Lead Open — site visit needed ASAP OAC5 Fab Lead needs Facade Lead comments. Facade Lead wants site visit to finalize.
5/27 🟠 HIGH Gym glass wall header — scope active APM / AGG Glass In Progress TBD OAC5 AGG Glass (Owner's contractor) shop drawings in progress.
5/27 🟠 HIGH Door Vendor jib door specs — millwork sequencing APM In Progress TBD OAC5 Part of millwork sequencing. APM to confirm specs.
5/27 ✅ RESOLVED Sheet piles — wall gap closure APPROVED APM / Site Super ✅ APPROVED 5/27 Done OAC5 PM sent 5/26. Owner Rep approved at OAC5.
5/27 ✅ RESOLVED Culligan water filtration — DECIDED PM ✅ DECIDED 5/27 Done OAC5 Owner Rep: RO to main kitchen faucet + $999 UV button upgrade.
5/27 ✅ RESOLVED Propane tank — delivered PM ✅ RESOLVED Done OAC5 Delivery this week, no storage charge.
5/27 📅 SCHEDULE Next OAC — June 3, 2026 at 11:00 AM All Scheduled 6/3/2026 OAC5 Confirmed.
# Category Task Owner Status Due Source Notes
1.0 ✅ RESOLVED Gas revision — MEP Eng email approved 5/6, hard copies to follow MEP Eng ✅ APPROVED 5/6 5/6/2026 OAC2 CRITICAL MILESTONE. Gas revision was the master blocker. Walls can now proceed to close on 2nd floor. 2 signed/sealed hard copies still needed for city submission.
2.0 ✅ RESOLVED HVAC pre-drywall walk — completed 5/6 with HVAC Lead APM/Site Super ✅ DONE 5/6 5/6/2026 Task List + OAC2 Walk complete. New punch list from walkthrough: bed 1 drain, access panels, VIP filter slot, bed 2 damper filter racks. Site Super working remaining items.
3.0 ✅ RESOLVED Framing inspection — passed (except staff/service wing) Site Super ✅ PASSED (partial) Prior Inspections sheet Passed except Staff Area/Service Wing. Service wing needs correction.
4.0 ✅ RESOLVED City inspector — met, EOR engineer letter in progress Site Super/APM ✅ MET 5/4/2026 Task List Met with inspector. Recall inspection of front stairs + at-grade landing slab needed. Site Super getting EOR structural engineer letter.
5.0 ✅ RESOLVED Condensate lines — horizontal insulation materials arrived 5/1 Site Super/HVAC Lead ✅ Materials on site 5/1/2026 Task List Materials arrived 5/1. Site Super making HVAC Lead insulate horizontal condensate lines.
6.0 ✅ RESOLVED Remote AC sensors — locations given to HVAC Lead at 5/6 walkthrough APM/Site Super ✅ DONE 5/6/2026 Task List Locations given to HVAC Lead at walkthrough. HVAC Lead will install.
7.0 ✅ RESOLVED All fresh air dampers — HVAC Lead confirmed installed and working 5/6 HVAC Lead ✅ CONFIRMED 5/6/2026 Task List Confirmed with HVAC Lead at walkthrough.
8.0 ✅ RESOLVED Lighting Designer — exterior sconce locations marked outside massage balcony APM/Site Super ✅ DONE (low one pending) 5/6/2026 Task List Done except low one on side of walkway.
9.0 ✅ RESOLVED Return for guest bed 1 from corridor — the PE approved, in progress Site Super ✅ In Progress ASAP Task List the PE approved. Site Super in progress. Also needs to draw from hallway plenum per the engineer.
10.0 🔴 CRITICAL Wellness Center HVAC — upsize to 3 ton, new condenser (DECIDE 5/13) APM/MEP Eng Open — Awaiting Calcs 5/13/2026 OAC2 Existing 1.5 ton vs ~33K BTU load. New condenser + MEP revision required. the PE + MEP consultant running calculations. Keep ceiling open.
11.0 🔴 CRITICAL Gas revision hard copies — 2 signed/sealed to city MEP Eng Open ASAP OAC2 Email approved 5/6. City still needs 2 signed and sealed hard copies submitted.
12.0 🔴 CRITICAL Roof HVAC isolators — Mech Eng draft → HVAC Lead review → EOR stamp → city PM/APM In Progress ASAP OAC2 PM reviewing draft with HVAC Lead. Then EOR stamp. Then process with city.
13.0 🔴 CRITICAL His & Hers stone — GC needs area list for shop drawings PM Open ASAP Task List GC wants list of which bathrooms get stone first to start shop drawings. PM to make 2nd floor slab area list and email GC + APM.
14.0 🔴 CRITICAL Interior painting — pricing proposal under review (Owner Rep confirmed) APM/PM Open — Action Required ASAP OAC2 + Owner Rep 5/4 Leveling doc to ownership this week. Painting Sub ~$10K cheaper, fewer COs. If declined: remove closets or third bid.
15.0 🔴 CRITICAL Front stairs — recall inspection, EOR engineer letter Site Super Open ASAP Task List City inspector needs evidence. Site Super getting EOR structural engineer letter.
16.0 🔴 CRITICAL Floor boxes — eliminate wellness boxes pending MEP revision APM/PM Partial Approval ASAP OAC2 5/6 Approved by Owner Rep except wellness room. Cannot finalize until wellness MEP revision done.
17.0 🔴 CRITICAL Wellness center MEP revision (240V? No hyperbaric?) MEP Eng/the PE Open 5/13/2026 OAC1 + OAC2 MEP revision required for wellness room electrical. MEP Eng following up with the PE. MEP consultant comments 5/6.
18.0 🔴 CRITICAL HVAC HVAC Lead punch list from 5/6 walk — 4 items HVAC Lead/Site Super Open 5/13/2026 Task List walkthrough results 1) Bed 1 drain blocking filter 2) Relocate access panels bed 1 & 3 3) VIP suite filter slot (Fab Lead) 4) Bed 2 damper blocking filter racks — Fab Lead to change all ceiling AHU filter racks.
19.0 🔴 CRITICAL Bed 3 service wing framing — failed inspection, correction needed Site Super Open ASAP Inspections sheet Framing inspection passed except staff/service wing. Correct and recall.
20.0 🔴 CRITICAL Plumbing sub — formal notice still required APM/PM Open ASAP Site Super control board Pattern documented. Escalation path under review.
21.0 🟠 HIGH Carousel mock-up — 5/7 at 2pm (Fab Lead bending metal bar) APM/Fab Lead/Interiors Lead Scheduled 5/7/2026 OAC2 Brass inlay edge detail + deflection assessment with black tile. Interiors Lead reviewing. Written confirmation of pricing + credit needed.
22.0 🟠 HIGH 2nd floor soffit alignment issues — site walk 5/7 Site Super/APM Scheduled 5/7/2026 OAC2 Owner videos flagged misalignments. Resolve during site walk. Document corrective actions.
23.0 🟠 HIGH Facade Lead on site 5/7 to discuss facade metals with Site Super MEP Eng/Site Super Scheduled 5/7/2026 OAC2 Brake metal: MEP Eng sent marked-up shop drawings 5/6 evening. Fab Lead to site measure + samples. Owner Rep color approval needed.
24.0 🟠 HIGH Landscape — Landscape Arch on site 5/7, 2 signed/sealed copies for city APM Scheduled 5/7/2026 OAC2 Landscape Arch bringing plans for city processing.
25.0 🟠 HIGH Metal fencing — hidden areas to pickets, decorative at visible, add screens APM/Fab Lead Open 5/13/2026 OAC2 Marked drawings needed: decorative vs picket by location. Also add privacy screens for garage electrical panels + exterior water heaters + Jandy panels.
26.0 🟠 HIGH Civil engineer — Site Super sketch to reduce fees Site Super/APM In Progress 5/13/2026 OAC2 APM spoke to Civil Eng. Site Super sending sketch to reduce scope/fees.
27.0 🟠 HIGH Safe room doors — written quote, pick certified installer PM Open ASAP OAC1 + OAC2 Will come back with quotes per OAC2. Must pick installer before safe room door supplier can make shop drawings.
28.0 🟠 HIGH Millwork Co. — phased delivery discussion, Owner Rep watching PM Open ASAP Task List Owner Rep asking for delivery target date. PM to contact the Millwork Co. rep about phased delivery.
29.0 🟠 HIGH Tub filler + drain — her master bath, core drill + rough Site Super/Plumber Open ASAP Task List Site Super to core drill. Plumber installs rough in floor.
30.0 🟠 HIGH Anti-scalding valve — her master bath (inspector requires) PM/Plumber Open ASAP Task List PM sending detail. Plumber will find spot after rough is in floor.
31.0 🟠 HIGH Freon lines master mech closet — lower (told HVAC Lead at 5/6 walk) HVAC Lead/Site Super Open ASAP Task List Told HVAC Lead at walkthrough. Follow up to confirm.
32.0 🟠 HIGH Seal access panel back of elevator shaft Site Super Open ASAP Task List Site Super ordering panel that seals/locks. Confirm lock with PM before ordering.
33.0 🟠 HIGH Lighting Designer — 1st floor walk scheduled 5/20 APM/Site Super Scheduled 5/20/2026 Task List After Lighting Designer completes 2nd floor. Site Super meets Lighting Designer for 1st floor schedule.
34.0 🟠 HIGH HVAC Lead — 1st floor HVAC walk scheduled 5/20 APM/Site Super Scheduled 5/20/2026 Task List Coordinate with 1st floor electrical walk.
35.0 🟠 HIGH Stair ceiling mirror — rosette detail, drawings from the Architect in Procore MEP Eng/APM Open 5/13/2026 OAC2 Wood rosette to conceal chandelier lift. Millworker wood frame + separate mirror vendor. Latest drawings from the Architect in Procore.
36.0 🟠 HIGH NWF — gym floor proposal owed PM Open ASAP Task List NWF owes gym floor proposal. PM to follow up.
37.0 🟠 HIGH File front door — Cladding Vendor to provide NOA PM Open ASAP Task List NOA needed for permit.
38.0 🟠 HIGH File garage door — NOA from the door vendor, then complete inspection PM Open ASAP Task List Get NOA then finish inspection.
39.0 🟠 HIGH Shearwall — pedestals shop drawing for exterior wood deck PM/APM In Progress ASAP Task List Comments sent 5/1. Shop drawing needed for pedestals.
40.0 📅 SCHEDULE New schedule — after 2F drywall + stone coordination APM/Site Super/PM Open After drywall progress OAC2 5/6 APM/Site Super/PM to build new schedule after completing 2F drywall and coordinating flooring install on 2F.
41.0 📅 SCHEDULE Next OAC — 5/13/2026 at 12:00 PM or 12:30 PM All Scheduled 5/13/2026 OAC2 Proposed time change from 1:30pm to noon or 12:30.
NEW 🟠 HIGH Camera payment — responsibility clarified (GC) APM Open ASAP Site Super control board / CM Camera scope and payment responsibility clarified — sits with the GC.
NEW 🟠 HIGH Pool equipment payment — through GC accounting APM / GC accounting Open ASAP CM update 5/6 Pool contractor approved. All equipment payments to be processed through GC accounting (GC accounting). Not a CM action item.
NEW 🟠 HIGH Epoxy coating samples — acquire and have on site for owner review APM Open 5/13/2026 OAC 5/6 + CM update Engage epoxy vendor or specialist. Obtain epoxy floor coating samples for garage. Owner must review samples on site before decision. Coordinate with Interiors Co. walkthrough on garage cabinetry.
NEW 🟠 HIGH Jib doors for AC mech closets — APM to review Door Vendor product + pricing APM Open 5/13/2026 CM update 5/6 Two jib doors: one inside chef's kitchen AC mech closet, one just outside. These are BASIC (non-custom) doors now in the drywall scope — NOT Millwork Co. millwork. PM priced from Door Vendor. APM to review Door Vendor product and pricing.
NEW 🟠 HIGH AV Room HVAC — clarify exact equipment needed APM Open 5/13/2026 CM update 5/6 APM to determine exact equipment spec for AV room HVAC. Not a CM item. Include in APM's tracker.
NEW 🟠 HIGH Millwork Co. installer — APM + Site Super + Owner Rep to decide on site APM / Site Super / Owner Rep Open Next joint site visit CM update 5/6 APM and Site Super to discuss with Owner Rep directly next time all three are on site. Decision: current installer candidate vs. GC sourcing another. Must be agreed in person — not via email or OAC.
NEW 🟠 HIGH Garage cabinetry decision — cover in Interiors Co. walkthrough Interiors Co. / PM / APM Open Next Interiors Co. visit OAC 5/6 + CM update Determine in Interiors Co. walkthrough whether any garage cabinetry design is needed. Separately: Epoxy vendor samples must be on site for owner review. Both items to be addressed together.
NEW 📋 INFO AGG Glass Contractors — gym glass wall shop drawings in progress CM / AGG Glass In Progress Post-drywall inspection CM update 5/6 AGG Glass Contractors (Owner's contractor) handling gym glass wall. Initial shop drawings underway. Final measurements require finished wall, ceiling, and floor. Then fabrication. GC to ensure room completion is sequenced accordingly.
NEW 📋 INFO Shower enclosures / ribbed glass / mirrors — Glass Vendor + PM + APM APM / PM Open TBD CM update 5/6 CM has no role. Assign to APM and PM. RFPs sent to three fabricators. GC to manage selection process.
5/13 ✅ RESOLVED Interior priming — APPROVED to start week of May 18 APM / PM ✅ APPROVED 5/13 5/18/2026 OAC3 5/13 Decision made at OAC3. Painter to mobilize week of May 18.
5/13 ✅ RESOLVED Propane tank anti-flotation drawings — Mech Eng completed MEP Eng ✅ DRAWINGS COMPLETE 5/13/2026 OAC3 5/13 Stamped drawings ready. Now needs to be processed with city.
5/13 ✅ RESOLVED Main house transformer reorientation — REJECTED ✅ CLOSED 5/13/2026 OAC3 5/13 Too costly + FPL 8-foot clearance required. Orientation stays as-is.
5/13 🔴 CRITICAL Cryotherapy chamber — 230V vs 208V conflict, transformer noise, heat load APM / the PE Open — Researching Alt. 5/20/2026 OAC3 5/13 Cryofast unit requires 230V, house provides 208V. Noisy transformer required. 2-5kW heat load. Research 208V American units and split-unit options. Send Owner Rep specs.
5/13 🔴 CRITICAL Deck & fire pit substructure — Struct Eng engineered drawings URGENT Struct Eng Open — Crew Waiting ASAP OAC3 5/13 Pedestals have no NOA. New plan: PT wood substructure by Struct Eng. Drawings are priority — crew will stop without them.
5/13 🔴 CRITICAL Drywall screw inspection — pass by end of week 5/11 Site Super In Progress 5/14/2026 OAC3 5/13 Plumbers on site May 14 to complete so ceilings can close.
5/13 🔴 CRITICAL Facade/brake metal — color decision needed to proceed MEP Eng / Fab Lead Open — Color TBD 5/20/2026 OAC3 5/13 Fab Lead's engineer reviewing fastening details. Color must be decided before shop drawings can be finalized.
5/13 🟠 HIGH City handrails — front steps + fire pit steps (new requirement) MEP Eng Open 5/20/2026 OAC3 5/13 City courtesy walk resulted in minor handrail additions required. MEP Eng to incorporate into fencing revision.
5/13 🟠 HIGH Roof fencing VE — white/less expensive alternative MEP Eng / Fab Lead In Progress 5/20/2026 OAC3 5/13 AOR opposed black fencing on white roof. Owner Rep concerned about appearance. Explore less expensive white solution. MEP Eng to get VE marked-up drawings from Fab Lead.
5/13 🟠 HIGH Landscape tree locations — conflict with underground utilities APM / Landscape Arch Open 5/20/2026 OAC3 5/13 Trees on landscape plan conflict with underground utilities. Site walk needed with landscape architect.
5/13 🟠 HIGH Tile sub installer on site May 14 + Tile Lead starts May 15 Site Super / APM Scheduled 5/14–5/15 OAC3 5/13 Exterior stone installer kickoff also May 15. Pool contractor job walk May 15.
5/13 🟠 HIGH Carousel — negotiate price + Tile Sub installation method meeting May 14 APM / PM In Progress 5/14/2026 OAC3 5/13 Brass inlays expected May 14. Meet Tile Sub to approve installation method.
5/13 🟠 HIGH Noisy transformer — find insulated location, get specs from Lighting Designer APM / Lighting Designer Open 5/20/2026 OAC3 5/13 Possible cryo unit transformer described as 'jet engine' loud. Must find new location.
5/13 🟠 HIGH Interiors Co. — master carpet selection + bathroom 2 digital slab layout Interiors Lead / Interiors Co. Open 5/20/2026 OAC3 5/13 Interiors Lead to push Interiors Co.. Owner Rep to be involved in carpet selection.
5/13 🟠 HIGH Electrician proposal for step-up transformer — get and review with Owner Rep APM Open 5/20/2026 OAC3 5/13 Obtain electrician's proposal for transformer. Share with Owner Rep for decision.
5/13 📅 SCHEDULE Next OAC — May 20, 2026 at 12:00 PM All Scheduled 5/20/2026 OAC3 5/13 Week of May 25 to be scheduled earlier for Owner Rep.
5/18 ✅ RESOLVED Drywall screw inspection — 2ND FLOOR PASSED 5/18/2026 Site Super / Door Vendor Drywall ✅ PASSED 5/18 5/18/2026 Daily Log 5/18 CRITICAL MILESTONE. Entire 2nd floor passed. Door Vendor adding 10 finishers 5/19. 1F drywall starts 5/19. Backing installation begins 1F.
5/18 🔴 CRITICAL Plumbing sub — ABSENT 6 CONSECUTIVE DAYS (5/11–5/18). Formal notice NOW. APM / PM Open — Formal Notice Required IMMEDIATE Manpower Log 5/18 Zero presence 5/11 through 5/18. Door Vendor starts 1F tomorrow. Condensate drains and tub/shower roughs must be done before ceilings close or they get drywalled in permanently.
5/18 🔴 CRITICAL HVAC sub — absent 5/13–5/18. HVAC punch items must clear before 1F ceiling closure. APM / HVAC Lead Open — Escalate IMMEDIATE Manpower Log 5/18 6 consecutive absences. HVAC punch list from 5/6 walk still open. Must clear before 1F ceilings close — bed 1 drain, access panels, VIP filter slot, bed 2 damper racks.
5/27 🔴 CRITICAL Veneer approval — TIME CRITICAL before June 15 Millwork Co. 2F Interiors Lead / Owner Rep / Interiors Co. Open — URGENT BEFORE 6/15 OAC5 Must approve: her closet, his & her vanities, massage vanity, cabana bar. June 15 is hard deadline.
5/27 🔴 CRITICAL Gas Rough Inspection — TODAY 5/27. Pass = call 1F Framing Site Super / MEP Eng Inspection Today 5/27/2026 OAC5 If gas passes today, call 1F framing inspection immediately.
5/27 🔴 CRITICAL Back deck structural / shearwall (Struct Eng) — under review APM / Struct Eng / GC Open — Under review This week OAC5 Drawing interpretation vs. cost responsibility under review. Struct Eng coming this week.
5/27 🔴 CRITICAL FPL Easement — retrieve, notarize, submit Miami-Dade CM Open ASAP OAC5 Covenant from neighboring property. Must retrieve → notarize → submit to county before FPL relocates transformers.
5/27 🟠 HIGH Interior louvers — bottom detail unresolved Facade Lead / Fab Lead Open — site visit needed ASAP OAC5 Fab Lead needs Facade Lead comments. Facade Lead wants site visit to finalize.
5/27 🟠 HIGH Gym glass wall header — scope active APM / AGG Glass In Progress TBD OAC5 AGG Glass (Owner's contractor) shop drawings in progress.
5/27 🟠 HIGH Door Vendor jib door specs — millwork sequencing APM In Progress TBD OAC5 Part of millwork sequencing. APM to confirm specs.
5/27 ✅ RESOLVED Sheet piles — wall gap closure APPROVED APM / Site Super ✅ APPROVED 5/27 Done OAC5 PM sent 5/26. Owner Rep approved at OAC5.
5/27 ✅ RESOLVED Culligan water filtration — DECIDED PM ✅ DECIDED 5/27 Done OAC5 Owner Rep: RO to main kitchen faucet + $999 UV button upgrade.
5/27 ✅ RESOLVED Propane tank — delivered PM ✅ RESOLVED Done OAC5 Delivery this week, no storage charge.
5/27 📅 SCHEDULE Next OAC — June 3, 2026 at 11:00 AM All Scheduled 6/3/2026 OAC5 Confirmed.

OAC #6 — JUNE 3, 2026 (Most Recent)

#TopicStatus / DecisionAction ItemOwnerDueFlag
1Site Safety — Foyer ceiling platformScaffolding insufficient; platform needed for accessSite Super's team to build access platform for high foyer ceilingSite SuperASAPACTION
2Civil revision — Civil EngExpected EOW (6/6/2026); MEP Eng sent latest site civil drawingFollow up; re-send civil specs for driveway subgrade to paving contractorsMEP Eng / Civil Eng6/6ACTION
3Irrigation meter — not on-siteMeter shown on drawings does not exist on-siteRequest from city; coordinate Landscape Arch (landscape) + irrigation subAPM / Landscape ArchASAPACTION
4Driveway drainage strategyPlan: solid concrete + 4-inch gaps every 4 ft as distributed drainsConfirm with Civil Eng if additional linear drains needed; clarify outflow pathCivil Eng / MEP EngEOWACTION
5Driveway slab spec6-inch slab; 12-inch stabilized subgrade; stainless welded rebar; compaction requiredRe-send specs EOW; align paving contractors; conduct compaction testsMEP Eng / APMEOWACTION
6Facade band shop drawings — MEP EngSent post-OAC5; receipt unconfirmed due to audio issuesVerify MEP Eng received; resolve any review issuesMEP Eng / PMASAPACTION
7Roof HVAC isolators — city permitSubmitted to city; approval expected week of 6/8/2026Await approval; schedule isolator install; then final roofing coatPM6/8ACTION
8Pool equipment screeningLandscaping vs removable breathable screen; heater-on-stand RFI still openDiscuss + decide with Landscape Arch + Fab Lead; resolve heater RFI; confirm clearance from windowAPM / Fab Lead / Landscape ArchASAPACTION
9Louvers — bottom gap + corner detail3/4" vs 1/2" gap debated; corner 'kissing' layout unresolvedCommunicate to Fab Lead; measure after stone install; study corner conditionFab LeadPost-stoneACTION
10Back deck / fire pit — scope + drawingsReviewed; minor comments from the designer + the engineer; scope package sent 6/2Schedule walkthrough; fire pit can start; price concrete pour vs PT woodSite Super / the engineerASAPACTION
11Back deck — revised spec16-inch spacing (was 18"); stainless concealed clips; Ipe biscuit clipsIssue revised drawings; owner approval needed on concrete pour optionSite Super / CMASAPACTION
12Spiral stair slab fill / trench repairRepair needed near stair trench; MUST go through B&ISpeaker 6 to follow up with B&I contact — URGENTB&I / Speaker 6URGENT🔴 CRITICAL
13Veneer approvals — Owner RepHis+hers vanity, massage vanity, cabana boxes (eucalyptus/teak) PENDINGGet Owner Rep approval BEFORE June 15 Millwork Co. deadline — TIME CRITICALCM / Owner RepBEFORE 6/15🔴 CRITICAL
14Chandelier location — her master closetInteriors Co. to provide dimensions; painting on HOLD until settledCoordinate Interiors Co. + Interiors Lead today (6/3); unblock paintingInteriors Co. / Interiors Lead6/3🔴 CRITICAL
15Culligan water filtration✅ APPROVED by CM on 6/3/2026No action.Done✅ DONE
16Sheet pile — permit required?Recollection: no permit required; explicit confirmation neededConfirm with building official next weekPM6/10ACTION
17Slabs to the fabricator's shopMoving Friday 6/6; Stone Sub to coordinate the inspector inspectionStone Sub calls the inspector for inspection coordinationStone Sub / the inspector6/6ACTION
18Propane tank✅ DELIVERED on-site (confirmed OAC5/OAC6)No action.Done✅ DONE
19Garage doors — high-lift systemProposal APPROVED; rails to install first; doors/cladding afterInstall rails; verify space for rigid insulation behind doorsSite SuperASAPACTION
20Spiral stair railing mock-upWell-received; minor end cap/termination + curve hiding concreteReview with Interiors Lead today (6/3); document photos/notes; finalize terminationInteriors Lead / Site Super6/3ACTION
21Next OAC — June 10, 2026Scheduled 6/10/2026 at 11:00 AM; site walk immediately afterAll parties attend; site walk to followAll6/10/2026SCHEDULE

OAC #5 — MAY 27, 2026

Attendees: PM, Site Super, APM (lead PM), Crowncore (CM), GC engineer, MEP Eng, Owner Rep, Facade Lead

# Topic Status / Decision Action Item Owner Due Flag
1.0 Safety — Platform leg at top of stairs RESOLVED — temporary for plywood subfloor, replaced. No action. Site Super Done DONE
2.0 Site cleanliness / Windows the engineer noted exterior spots being addressed. Windows must be closed EOD. Enforce daily. Site Super Daily INFO
3.0 Civil revision — Civil Eng Still pending full civil revision. Civil Eng issued grading plan without 'not for construction' note. Follow up with Civil Eng. MEP Eng / Civil Eng 6/3 ACTION
4.0 Facade horizontal metal specs PM sent to MEP Eng today for review. MEP Eng to confirm. MEP Eng 6/3 ACTION
5.0 Wellness — Cryotherapy conduits Proceeding with Cryo Vendor directing conduit placement. APM calls Cryo Vendor back to site to mark exact locations. APM / Cryo Vendor ASAP CRITICAL
6.0 Landscape — Landscape Arch / LAND Sunshine 811 scheduled to mark seawall area this week. Site walk with Landscape Arch/Site Super after. Confirm 811 markings then schedule walk. APM / Site Super This week ACTION
7.0 Roof HVAC isolators — permit submission Signed permit app received back. Will now submit to city. Submit to city immediately. PM ASAP ACTION
8.0 Fencing / railings VE CM issued instructions on sections. Final proposal from Fab Lead pending. Obtain final proposal from Fab Lead. PM / Fab Lead 6/3 CRITICAL
9.0 Interior louvers — bottom detail Fab Lead needs Facade Lead comments on shop drawings. Facade Lead wants site visit. Schedule Facade Lead site visit to finalize. Facade Lead / Fab Lead ASAP ACTION
10.0 Shearwall — back deck / fire pit Struct Eng coming this week. Monitor. Push for delivery. APM / Struct Eng This week ACTION
11.0 Shearwall — column under wellness room Drawings received today. Sent to Facade Lead & EOR for approval. Await Facade Lead / EOR. Facade Lead / EOR ASAP ACTION
12.0 Cabana bath door — shop drawings + NOA Pending. CM P to send to team. CM to provide. CM ASAP ACTION
13.0 Pool Co. — pool heater / window conflict Pool equipment delivered yesterday. Pool Tech coming for layout. Schedule Pool Tech for equipment layout. Pool Tech / APM ASAP ACTION
14.0 Veneer — owner approval ⚠ TIME CRITICAL STILL PENDING: her closet / his & her vanities / massage vanity / cabana bar. Interiors Lead coordinating once new samples arrive. Must approve BEFORE June 15 Millwork Co. 2F delivery. Interiors Lead / Owner Rep / Interiors Co. BEFORE 6/15 CRITICAL
15.0 Safe room doors — 2 installations GC office requested COI from installer. Follow up on COI. Route to ownership once confirmed. PM ASAP ACTION
16.0 Culligan water filtration — DECIDED DECIDED by Owner Rep: RO attached to main kitchen faucet + $999 UV button upgrade. Proceed per direction. PM Done DONE
17.0 Driveway proposals Still leveling. Will send to ownership for approval. Complete leveling. Route to ownership. PM / APM 6/3 ACTION
18.0 Sheet piles — wall gap closure — APPROVED APPROVED. PM sent proposal 5/26. Owner Rep approved at OAC5. Proceed with installation. APM / Site Super ASAP DONE
19.0 Slabs from Detroit Glass Vendor inspecting tomorrow (5/28). Glass Vendor to inspect and report. Glass Vendor 5/28 ACTION
20.0 Sill risers Site Super ordering from the supplier. Confirm delivery date. Site Super ASAP ACTION
21.0 Propane tank delivery — RESOLVED Delivery this week, no storage charge. No action. PM Done DONE
22.0 Tape & finish — 2nd floor In progress. Monitor. Site Super / Painting Sub Ongoing INFO
23.0 Millwork Co. — schedule revision ⚠ Millwork Co. rep on site. Revised: 2F FIRST. June 15 — 2nd floor vanities. Confirm veneer approval before June 15 delivery. APM / Millwork Co. rep 6/15 CRITICAL
24.0 El Gant — exterior stone starts June 15 Confirmed. Confirm start. El Gant / Site Super 6/15 ACTION
25.0 Tile Sub — waterproofing On site. Monitor. Tile Sub / Site Super Ongoing INFO
26.0 Tile Lead Tile — kickoff Came today. Coming Monday for layout then waterproofing. Confirm Monday appointment. Tile Lead / Site Super 6/1 ACTION
27.0 Swimming pool — float slab Need to float slab under equipment. Pool Sub owes proposal. Chase Pool Sub. PM / Pool Sub ASAP ACTION
28.0 1F pre-drywall mechanical walk Site Super has HVAC Lead's list and is working items. Complete items before walk. Site Super / HVAC Lead TBD ACTION
29.0 1F pre-drywall low voltage walk Walk done with LV Sub. Working on list. Complete items. Site Super / LV Sub TBD ACTION
30.0 Gas rough inspection — TODAY 5/27 Inspection TODAY. Pass → call 1F framing inspection. Confirm pass/fail. Call framing if gas passes. Site Super / MEP Eng 5/27 CRITICAL
31.0 Electrical — 1F rough ~2–3 more weeks for Lighting Designer to complete 1F rough. Monitor. Lighting Designer / Site Super ~6/17 ACTION
32.0 City storm drain cleaning City rep out until 6/1. Follow up 6/1. Site Super 6/1 ACTION
33.0 Mosquito misting trims Coming next Wednesday for test fit. Confirm. Site Super 6/3 ACTION
34.0 Exterior speakers + light trims Coming from AV Vendor / trims ordered. Confirm arrival and install schedule. APM / AV Vendor TBD ACTION
35.0 FPL easement — recording Covenant signed. Need to record. CM: retrieve from neighboring property → notarize → submit Miami-Dade. CM ASAP CRITICAL
36.0 Next OAC meeting June 3, 2026 at 11:00 AM. Confirm attendees. All 6/3 SCHEDULE

OAC #4 — MAY 20, 2026

Attendees: PM, Site Super, APM, CM, GC engineer, MEP Eng, MEP consultant, the PE, Owner Rep | Next OAC: 5/27 at 11:00 AM

# Topic Status / Decision Action Item Owner Due Flag
1.0 Safety — Elevator 2F Opening Site Super added fall protection at elevator opening 2F. Resolved. No further action. Site Super Done DONE
2.0 Site Cleanliness / Windows Drywall dust daily — Site Super enforcing sweep up. Windows MUST be closed at end of every day — rainy season. Enforce daily at closing. Site Super Daily INFO
3.0 MEP Revision — City APPROVED APPROVED. PM picked up from city 5/20. Resubmitted 5/18, approved same week. File approved plans. Proceed with gas tank and related work. PM Done DONE
4.0 Propane Tank Slab — Engineer Inspection the engineer needs to inspect slab once steel is in place. the engineer to inspect when steel ready. APM / the engineer Post-steel ACTION
5.0 Civil Revision — Civil Eng Still pending full civil revision. Civil Eng provided grading above propane tank. MEP Eng reissuing grading plan without Not For Construction label. Follow up with Civil Eng for target date. MEP Eng / Civil Eng 5/27 ACTION
6.0 Facade Metal — Color Decision Color to match window frames. Fab Lead providing. Shop drawings needed from Fab Lead for Facade Lead review. MEP Eng reaching out to Fab Lead for shop drawings. MEP Eng / Fab Lead 5/27 CRITICAL
7.0 Wellness Center — Cryotherapy DECIDED DECIDED: Owner Rep purchasing unit himself. Cryo Vendor installs after final inspections. Transformer in electrical room. Split condenser on roof low wall outside wellness room. APM calls Cryo Vendor back to site to give Site Super exact conduit needs and locations. APM / Site Super ASAP DONE
8.0 Landscape — Landscape Arch (surgery) Landscape Arch had surgery. Will contact APM when ready to walk. Call Sunshine 811 to locate underground infrastructure between pool deck and seawall before tree walk. APM Post-recovery ACTION
9.0 Roof HVAC Isolators — Ownership Signature EOR stamped. Permit app sent to ownership (ownership entity) for signature 5/18. STILL WAITING. Ownership to sign immediately. PM to follow up. Owner / PM ASAP CRITICAL
10.0 Fencing & Railings VE Facade Lead met Fab Lead 5/19. Preparing summary for Owner Rep on design changes and pricing. New city handrails needed at front and back stairs. Facade Lead presented to Owner Rep at OAC4. Still pushing to finalize VE. Finalize VE with Facade Lead. Fab Lead to produce shop drawings. Process with city. Facade Lead / Fab Lead 5/27 CRITICAL
11.0 Interior Louvers Fab Lead needs Facade Lead comments on shop drawings submitted. Facade Lead to review and comment. Then coming to site to discuss. Facade Lead / Fab Lead ASAP ACTION
12.0 Shearwall — Pool Deck & Fire Pit Working on engineering drawings. Pushing Struct Eng every few days. Critical to keep Ceiling Sub working. If Struct Eng slow — call EOR. Keep pushing Struct Eng. Alert EOR if no delivery by 5/27. APM / Struct Eng ASAP CRITICAL
13.0 Shearwall — Column Under Wellness Struct Eng addressing Facade Lead comments. Monitor. Struct Eng 5/27 ACTION
14.0 Cabana Bath Door — Shop Dwgs + NOA Shop drawings and NOA needed. Obtain shop drawings and NOA. PM / APM ASAP ACTION
15.0 Interiors Co. — Master Carpet Selection Interiors Co. to work with owner to select. Interiors Lead to push Interiors Co.. Owner Rep to decide. Interiors Lead / Interiors Co. 5/27 ACTION
16.0 Carousel Upcharge — REJECTED REJECTED by Owner Rep. Does not approve $3.2K + $750 upcharge. Owner Rep may revisit later. Drop current proposal. Close item for now. APM / PM Closed DONE
17.0 Safe Room Doors Confirm installer insurance before sending to ownership. PM to verify insurance then route to ownership. PM ASAP ACTION
18.0 Culligan Water Filtration Met on site 5/19. Proposal being sent to ownership. Route Culligan proposal to CM for owner approval. PM ASAP ACTION
19.0 Driveway Proposals Leveling in progress. Will send to ownership. Complete leveling. Route to ownership. PM / APM 5/27 ACTION
20.0 Millwork Co. — Vanity Veneer Owner Rep and Millwork Co. rep meeting 5/20 for veneer approval. Shipping vanities second week of June. One week transit. Vanity install 2F late June. Confirm Owner Rep approves veneer today. Track June shipping. Pending veneer approval. Owner Rep / Millwork Co. rep 5/20 CRITICAL
21.0 Exterior Wood Ceilings — Extra Wood RESOLVED: Ceiling Sub confirmed 5/20 — no additional wood planks needed to finish ceilings. No action. Site Super Done DONE
22.0 Slabs from Detroit Glass Vendor going to inspect. Will email results. Glass Vendor to inspect and report. Glass Vendor ASAP ACTION
23.0 Sheet Piles — Wall Gap On site. Installation pending Sunshine 811 locating underground. Call Sunshine 811. Proceed once cleared. APM / Site Super ASAP ACTION
24.0 Brass Floor Inlay Bars Received on site. Tile Sub to make carousel edge mock-up. Tile Sub to make mock-up with brass bars. Tile Sub / Site Super ASAP ACTION
25.0 Basemold Riglet On site. Blocked by sill riser installation. Chasing the window vendor. Chase the window vendor for sill risers. APM / PM ASAP ACTION
26.0 Propane Tank Delivery Dumpster relocated. Requesting delivery this week. Confirm delivery date. PM This week CRITICAL
27.0 Drywall Inspection — PASSED PASSED. Tape and finish in progress. Priming pushed back one week — dust + inspection timing. Painting Sub to start priming when ready — week of 5/25. Painting Sub / PM Week of 5/25 DONE
28.0 El Gant Kickoff — Exterior Stone El Gant kickoff meeting today 5/20. Commencing exterior stone installation. El Gant starting. El Gant / Site Super 5/20 DONE
29.0 Tile Sub — Waterproofing + Carousel Stone Sub starts waterproofing 5/21-22. Approved crack suppression plan. Warranty company to inspect. Thinks he has enough black slabs — to confirm. Tile Sub starts 5/21. Confirm black slab quantity. Tile Sub / Site Super 5/21 ACTION
30.0 Tile Lead Tile — 2 Bathrooms 2 bathrooms only. Pending Tile Lead measuring. Schedule Tile Lead to measure. PM / Tile Lead ASAP ACTION
31.0 Swimming Pool — Float Slab Equipment arriving ~2 weeks. Need to float slab under equipment — sloped. PM getting price from Pool Sub for slab float. PM / Pool Sub ASAP ACTION
32.0 Millwork Co. — Vanity Shipping Shipping second week of June. One week transit. Install 2F late June. Pending veneer approval 5/20. Track shipping. Confirm veneer approval. APM / Millwork Co. rep June CRITICAL
33.0 1F Pre-Drywall Mechanical Walk 5/21 at 10am — HVAC Lead AND the engineer MUST attend. APM to confirm HVAC Lead and the engineer attendance. HVAC Lead / the engineer / APM 5/21/2026 CRITICAL
34.0 1F Pre-Drywall Low Voltage Walk 5/21 at 12pm — LV Sub AND the engineer MUST attend. APM to confirm LV Sub and the engineer attendance. LV Sub / the engineer / APM 5/21/2026 CRITICAL
35.0 Pending Change Orders 'PM?' noted on agenda — no CO list provided at OAC4. PM to provide CO list before or at 5/27 OAC. PM 5/27 ACTION
36.0 New Master Schedule APM/Site Super/PM to build after 2F drywall and flooring coordination. Build schedule after 2F drywall complete and flooring sequenced. APM / Site Super / PM After 2F drywall ACTION
ADDITIONAL DETAIL FROM MEETING TRANSCRIPT — CROSS-REFERENCED 5/20/2026
A1 Civil — Slab Elevation Confirmation Needed Civil plan shows 'preliminary / not for construction' — shell contractor hesitant to proceed. Need written confirmation that bubbled area slab elevations (e.g. 7 NGBD) will not change. MEP Eng to get written confirmation OR have Civil Eng reissue bubbled sheet without preliminary stamp for propane tank/generator area only. MEP Eng: written elevation confirmation OR reissue bubbled sheet without preliminary stamp for propane/generator area. MEP Eng / Civil Eng 5/22/2026 CRITICAL
A2 Generator Screening + Fencing — Owner Package Due 5/25 Generator ~69 inches tall — must be elevated above flood level. City requires permanent screening (landscaping supplements only). Owner: white fences, minimalist, clean V-shape resort look. Rooftop: vertical tubes (lower cost) vs vertical fins (better concealment) — need apples-to-apples pricing. Pool fence minimum 48 inches. Cable rail vs vertical picket at pool equipment path — white finish preferred. Marina-to-pool deck gates required by city. Equipment stacking may exceed screen height — panels designed to be removable for service. Prepare user-friendly drawing + pricing summary for Owner Rep by 5/25. Include fence/screen options with clearances. Review MEP Eng drawing with city to confirm 3-foot clearances for generator + condensing unit. Bracket-mounted unit behind fence preferred — no new slab. APM / MEP Eng / Fab Lead 5/25/2026 CRITICAL
A3 Pool Equipment Layout — Field Meeting with Pool Co. (~2 weeks) Focused field meeting needed with Pool Tech (Pool Co.) to resolve pool equipment layout, gas water heater/window clearances, egress, and fence height within code. River rock preferred over slab for maintenance. Schedule field meeting with Pool Co. within ~2 weeks to finalize equipment layout and fence strategy. APM / Pool Tech (Pool Co.) ~6/3/2026 ACTION
A4 Wine Condenser Location — City Clearances Wine condenser placement needs code clearances. Consider consulting mechanical inspector. Alternative location feasible with fence extension — owner prefers no new slab. AV Vendor panel may be movable — verify code. Consult city mechanical inspector on wine condenser clearances. Verify AV Vendor panel movability. No new slab if possible. APM / MEP Eng 5/27/2026 ACTION
A5 Wellness Center — Cryotherapy Conduit Rough-In Detail Cryo Vendor's direction: rough-in conduits NOW (exterior conduit for condenser + conduit to electrical room for possible transformer) before final inspections. Install cryotherapy unit AFTER final inspections/occupancy to avoid MEP revisions. Prefer 208V outdoor split system. Avoid water-cooled units requiring chiller. UL listing not required for private residence post-occupancy — confirm with AHJ/insurance if non-UL unit considered. APM to call Cryo Vendor back to site to mark exact conduit locations for Site Super. Rough-in conduits before walls close. APM / Cryo Vendor / Site Super ASAP CRITICAL
A6 Culligan Water Treatment — DECIDED Culligan recommends: whole-house filtration + RO at kitchen only. NO dedicated RO or softener for steam shower — RO output ~1.8 gpm insufficient for ~2.0 gpm demand, plus space constraints. Owner agreed: proceed without RO/softener for steam. Domestic water split ground floor + 2F with constant-pressure booster pumps. Commission at farthest fixtures (master high-flow shower) with balancing valves. Send updated Culligan proposal to Owner Rep and CM for approval. Commission domestic water system at farthest points. Document pump control logic. PM / CM ASAP DECISION
A7 Facade Break Metal — Prior Scope Incorrect, Drawings Poor Prior shop drawings from Fab Lead had incorrect scope and poor drawing quality. Marked-up drawings were emailed. Fab Lead must re-review based on markups — not just the original submission. Resend marked-up drawings to Fab Lead. Fab Lead to re-review and resubmit corrected shop drawings. MEP Eng / Fab Lead 5/27/2026 CRITICAL
A8 Interior Louvers — Stone Connection Detail + On-Site Review Framing reportedly complete. Louver-to-stone connections needed — pin connection under stone. Interiors Co. provides design intent. On-site meeting needed to align details and expedite approvals. Schedule on-site meeting to finalize louver details. Provide timely approvals/comments to Fab Lead. MEP Eng / Fab Lead / Interiors Co. ASAP ACTION
A9 Shearwall Struct Eng — ULTIMATUM: Firm Timeline by EOD or Replace Owner instruction at OAC4: if Struct Eng does not provide firm timeline TODAY (5/20), engage alternate engineer known to Site Super. AOR (Facade Lead) to submit to city. EOR is the backup. PT wood substructure is the approach — must be engineered for hurricane/impact zone. City disallows plastic pedestals without NOI. Struct Eng: firm timeline by EOD 5/20 or REPLACE with alternate engineer. If replaced: Site Super's contact + EOR. AOR to submit to city. APM / Facade Lead / Struct Eng EOD 5/20/2026 CRITICAL
A10 Irrigation — Start Meter Process + Shop Drawings Start irrigation meter process now due to lead times. Irrigation subcontractor to produce shop drawings per Landscape Arch's plans. Landscape Arch to review/approve after recovery. Utility locating and exploratory excavation near seawall before Landscape Arch's site walk. Start irrigation meter process. Irrigation sub produces shop drawings. Utility locating before any excavation near sheet pile. APM / PM ASAP ACTION
A11 Ceiling Sub — Finish Ceilings This Week Then PAUSE Ceiling Sub crew to finish exterior wood ceilings this week. Then PAUSE — no next scope until vanities arrive AND deck/fire pit plans AND millwork are ready. Do not start new scope without all three in place. Site Super to confirm ceiling completion. Communicate pause instruction to Ceiling Sub. Site Super This week ACTION
A12 Master Carpet Selection — LOW PRIORITY Interiors Co. rep to confirm with owner. Low priority — not holding anything up. Interiors Co. rep to confirm with Owner Rep. No urgency. Interiors Co. / Interiors Co. rep Low priority INFO
A13 Roof HVAC Isolators — Ownership Signature via FedEx EOR stamped drawings complete. Permit app sent to ownership (ownership entity). Expected to arrive via FedEx for signature. Ownership to sign and return FedEx immediately upon receipt. Owner / PM Upon receipt CRITICAL

OAC #3 — MAY 13, 2026

Attendees: APM (lead PM), Site Super, MEP Eng, Owner Rep, Fab Lead, Struct Eng, the PE, Interiors Lead + others | Next OAC: May 20, 2026 at 12:00 PM

# Topic Decision / Outcome Action Item Owner Due Date Status
1.0 Site Safety & Cleanliness Sinkhole by garage repaired with concrete. Hard hats now enforced for GC crews. Site cleaned after drywall. Tracks vacuumed before insulation/drywall install. Strictly enforce window closure at end of each day — rainy season started. Protect new drywall. Site Super Daily Ongoing
2.0 Propane Tank Anti-Flotation Device Mech Eng completed drawings. Hard copies of MEP revision provided by MEP Eng. Process stamped anti-flotation device drawings with the city. MEP Eng / PM ASAP Open
3.0 Civil Revision — Civil Eng Civil Eng received site plan and city comments. Civil revision in progress. Follow up with Civil Eng on civil revision progress next week. APM 5/20/2026 In Progress
4.0 Facade / Brake Metal — Color Decision Needed Meeting held with Facade Lead on facade metal. Fab Lead's engineer reviewing markups on brake metal shop drawings to add fastening details. Color must be decided before work can proceed. Work with Fab Lead on facade metal color. MEP Eng to get final marked-up shop drawings from Fab Lead with VE changes. MEP Eng / Fab Lead / APM 5/20/2026 Open — Color TBD
5.0 Landscape Plan — Tree Relocation Landscape architect's plans show trees conflicting with underground utilities. Schedule walk-through with landscape architect to relocate conflicting trees. APM / Landscape Arch 5/20/2026 Open
6.0 City Courtesy Walk-Through Results City approved sheet piles for seawall gap. Minor handrail additions required on front steps and fire pit steps. MEP Eng to incorporate new handrail requirements into fencing revision. MEP Eng 5/20/2026 Open
7.0 Fencing & Railing VE — Roof Fencing Design Major VE discussion. City handrail requirements being incorporated. AOR opposed VE for roof fencing — original plan was high-end louver system to hide tall condensing units. Owner Rep: black fencing on white roof looks ugly. DECISION: explore less expensive, possibly white, fencing solution for roof and generator areas. MEP Eng to get final marked-up shop drawings from Fab Lead reflecting VE changes (pickets vs decorative, roof fencing solution). MEP Eng / Fab Lead 5/20/2026 In Progress
8.0 Wellness Center — Cryotherapy Chamber (CRITICAL ISSUE) Selected Cryofast machine (French) requires 230V. House provides 208V — noisy step-up transformer required. Unit generates 2–5 kW heat. Condenser system 6 at max. System 2 could handle at 120% capacity (needs owner approval). Three-phase electrical cannot be changed. Research American-made 208V cryotherapy units and split-unit options (external condenser/chiller) to avoid transformer + AC mods. Send Owner Rep picture + specs of proposed cassette unit. APM / Speaker 3 5/20/2026 Open — Researching Alt.
9.0 Wellness Center — AC Solution Engineer the PE proposed 1.5-ton supplemental cassette unit. Linear less-obtrusive cassette preferred for aesthetics. Investigate less obtrusive AC cassettes. Determine which rooms are served by condenser system 2. APM / the PE 5/20/2026 Open
10.0 Transformer Noise Issue Separate transformer (possibly cryo unit) identified as extremely noisy ('jet engine'). Must find new insulated location. Get technical specs for noisy transformer from Lighting Designer. Find suitable insulated location. APM / Lighting Designer 5/20/2026 Open
11.0 Main House Transformer Reorientation ✅ REJECTED — too costly, must maintain 8-foot FPL clearance. Orientation stays as-is. No action — closed. Closed ✅ Closed
12.0 Carousel Turntable — Pricing & Installation Proposal received. Price negotiation underway. Simple gear modification proposed to slow it down. Brass floor inlays expected May 14. Call carousel supplier to negotiate lower price. Meet with Tile sub installer May 14 to approve turntable installation method. APM / PM 5/14/2026 In Progress
13.0 Deck & Fire Pit Substructure — NOA Issue Originally planned pedestals have no NOA and are unapproved. New plan: pressure-treated wood substructure designed by Struct Eng. Drawings are priority to prevent work stoppage. Struct Eng to provide engineered drawings for PT wood deck and fire pit substructure. PRIORITY — crew waiting. Struct Eng ASAP Open — URGENT
14.0 Interior Painting — Priming Approved ✅ DECISION: Interior priming approved to start week of May 18. Coordinate painter mobilization for week of May 18. APM / PM 5/18/2026 ✅ Approved
15.0 2nd Floor Drywall Screw Inspection Goal: pass drywall screw inspection by end of week of May 11. Plumbers scheduled May 14 to complete work so ceilings can be closed. Plumbers on site May 14. Close ceilings after plumbing complete. Site Super / Plumber 5/14/2026 In Progress
16.0 Tiling — Tile Sub & Tile Lead Tile Sub (main installer) on site May 14. Second installer Tile Lead starts May 15. Exterior stone installer kickoff May 15. Coordinate Tile Sub May 14 start and Tile Lead May 15 start. Stone installer kickoff May 15. Site Super / APM 5/14–5/15/2026 Scheduled
17.0 Interiors Co. Input — Bathroom Digital Slab Layout + Master Carpet Interiors Co.'s input needed for bathroom 2 digital slab layout and master carpet selection. Interiors Lead to push Interiors Co. for master carpet selection with Owner Rep. Interiors Lead / Interiors Co. 5/20/2026 Open
18.0 Gym Glass Wall — Shop Drawings Shop drawings awaiting final ceiling layout and drywall inspection completion. AGG Glass to proceed with shop drawings once ceiling layout final and drywall inspection passed. CM / AGG Glass Post-drywall inspection Open
19.0 Safe Room Doors — Written Quote the designer provided verbal quote of $1.5K/piece. Written quote still pending. Get written quote from the designer for both safe room doors. PM ASAP Open
20.0 Shower Glass — Height Clarification Interiors Co. needs to clarify heights. Believed only steam room glass goes to ceiling. Speaker 10 (PM?) to receive all shower information from PM for framing. Interiors Co. to clarify. Interiors Co. / PM 5/20/2026 Open
21.0 Roof HVAC Isolators — Landscape Arch Follow-Up Follow-up needed with Landscape Arch regarding isolators. APM to follow up with Landscape Arch on roof HVAC isolators. APM 5/20/2026 Open
22.0 Material Status Update Riglets on site. Sheet piles on site. Slabs from Detroit in transit. Brass floor inlays expected May 14. Confirm brass floor inlay delivery May 14. Track Detroit slab delivery. APM / Site Super 5/14/2026 In Transit
23.0 Next OAC — May 20, 2026 at 12:00 PM Confirmed. All parties to attend. Week of May 25 OAC to be scheduled earlier for Owner Rep. All 5/20/2026 Scheduled

OAC #2 — MAY 6, 2026

OAC #1 — MAY 1, 2026

Complete Active / scheduled In progress Planned Critical hold Today
Phase / TaskOwnerStatus 4/14 4/21 4/28 5/5 5/12 5/19 5/26 6/2 6/9 6/16 6/23 6/30 7/7 7/14 7/21 7/28 8/4 8/11 8/18 8/25 9/1 9/8 9/15 9/22 9/29 10/6 10/13 10/20 10/27 11/3 11/10 11/17 11/24 12/1 12/8 12/15 12/22 12/29 1/5 1/12 1/19 1/26 2/2 2/9 2/16 2/23
LIFE SAFETY & CRITICAL HOLDS
⚠ Gas Revision — walls CANNOT close PM ⚠ Trouble
⚠ HVAC Supply Duct Failure — demand letter HVAC Lead PM ⚠ Trouble
Gas WH — Underground Elec. Conflict (CO~3wk) PM ⚠ Trouble
Front Facade — Stone vs. Paint DECISION PM ⚠ Trouble
ENVELOPE & EXTERIOR
Elevator — Rails + Permit ✅ Site Super ✅ Done
Remove Scaffolding Site Super ✅ Done
Stucco (stucco sub) — started 4/21 PM In Progress
Foam Panel Fabrication ✅ PM ✅ Done
Foam Panel Ext. Install PM Scheduled
Riglets T&G — powder coating (Wed) Site Super Open
LED Metal Strip — galvanize (DUE 4/29) Site Super Open
Aluminum Cladding Site Super Open
Wood Ceilings Site Super Open
Ext. Patio Stone PM Open
Stone Terraces Site Super Open
Glass Railings Site Super Open
Spiral Stair & Railings (release scope) APM Open
Retaining Wall — Public Works PM Open
Pavers / Driveways APM Open
Roof Metal Equipment Enclosure APM Open
MEP ROUGHS
Rough Wiring & Distribution ✅ Site Super ✅ Done
Low Voltage ✅ Site Super ✅ Done
Plumbing Rough (Plumbing sub — started 4/20) Site Super In Progress
⚠ Condensing line insulation scope — Horiz. TBD PM ⚠ Trouble
⚠ Wine Wall & AV HVAC Rough Site Super ⚠ Trouble
HWH / DOB Approvals PM Pending
Gas Piping (pend. inspection) Site Super In Progress
ELD Electrical — started 4/28 ✅ Site Super In Progress
ELD Metal — started 4/27 ✅ Site Super In Progress
Garage A/C Relocation APM Open
Transformer / Pedestals (Marina) PM Open
CIVIL & SITE
French Drain Relocation (Thurs 4/30) APM Scheduled
Pile Schedule + Inspection Site Super Open
Slab — Start + Rebar + Completion Site Super Open
Back Fill Site Super Open
Propane Tank — Survey + Delivery PM Open
Gas Tank Coordination PM Open
Pipe Work (City — clean, no lining) PM Open
POOL & EXTERIOR AMENITIES
Pool Equipment Release + Start APM Open
Pool Pedestals + Deck Shop Dwgs APM Open
Fire Pit Shop Drawings APM Open
Garage Doors — release for production APM Open
DRYWALL & SHELL CLOSE
Door Vendor Drywall — Master His/Her ✅ (ceilings + walls) Site Super ✅ Done
Drywall Finish (7 days) Site Super In Progress
Framing Inspection Site Super Open
Drywall — All Areas Site Super Open
Plaster / Compound / Cornerbeads Site Super Open
MILLWORK & FINISH TRADES
Millwork Production (underway) PM In Progress
Tile Sub Stone — Material→Layout→Cut→Install PM Open
Stone Backing + Vanity L-Angles (dates TBD 🔴) PM Open
Millwork Co. (vendor contact — June 2026) Site Super Open
Floor Heating — Material Ordered 4/21 ✅ PM ✅ Done
Millwork Install Site Super Open
Closets Site Super Open
Doors & Casing Site Super Open
Counters Site Super Open
Appliances PM Open
FLOORING
Stone Flooring & Bathrooms Site Super Open
Wood Flooring Delivery + Install Site Super Open
Flush Baseboard (Tri-County) Site Super Open
ELECTRICAL & MEP FINISHES
HVAC — Master Wing (owner approval) PM Open
Steam Room Lighting (owner confirm) PM Open
Electrical Trim / Keypads / Fans APM Open
Mechanical Finishes APM Open
AV VENDOR — shade wire/alarms/speaker Site Super Open
CONTRACTS & APPROVALS
Interior Painting — revise + resend proposal PM Open
Exterior Painting — new proposal (25% darker) PM Open
Paint Selections — OWNER APPROVALS NEEDED 🔴 PM ⚠ Trouble
Electrical Fixtures — AV Vendor confirm scope Site Super Open
INTERIOR FINISHES
Final Painting PM Open
Specialty Wall Finishes APM Open
Shower Glass & Mirrors APM Open
Door Hardware + Window Treatments APM Open
Stair Finishes / Rail APM Open
Carpet APM Open
CLOSEOUT
Rolling Punchlist (start Dec 2026) APM Open
TCO Application PM Open
Testing & Balancing / Commissioning APM Open
Cleaning / De-mob / Close Out APM Open
🎯 TARGET COMPLETION — FEB 28, 2027 GC 🎯 TARGET
In Progress Scheduled Planned

ROUGH INSPECTIONS

Low Voltage✅ Passed · AV Vendor
Windows Buck - Anchoring✅ Passed · Window Vendor
Roof In Progress✅ Passed · inspector
Mechanical Rough✅ Passed · SE Mechanical
Fire Alarm Rough✅ Passed · Electrical Sub
Framing Rough✅ Passed (except Staff/Service Wing) · Passed except Staff Area / Service Wing · GC
Insulation✅ Passed — 4/14/2026 · Icynene at roof slab · JAJ
Drywall Screw — 2nd Floor✅ PASSED — 5/18/2026 · CRITICAL MILESTONE. Entire 2nd floor passed. · Door Vendor Drywall
Plumbing Rough (shower pans & insulation)✅ Passed — 4/16/2026 · Gym & Master Shower Pans / Pipe insulation · Plumbing sub
Gas Rough🔴 TODAY — 5/27/2026 · Scheduled today. Pass → call 1F Framing inspection. · Plumbing sub
Electrical Rough⏳ Partials · Pending Ground Floor & Garage (~2–3 more weeks) · Electrical Sub / Lighting Designer
1F Framing Inspection⏳ PENDING GAS PASS · Will call immediately if gas rough passes today (5/27). · GC

UPCOMING INSPECTIONS

Wall InsulationUpcoming
Drywall Screw — 1st FloorUpcoming — after 1F rough complete
Roof FinalUpcoming
Plumbing FinalUpcoming
Electrical FinalUpcoming
Mechanical FinalUpcoming

SCOPES MISSING TO CLOSE

Guest Bath 3Smart Glass — unknown if being done
Guest Bath 3Blocking at ceiling (in case client wants later)
Guest Bath 3Window removal/reinstall — pending decision
Guest Bath 3Pipe Insulation
Guest Bath 3Wall Insulation
Guest Bed 3Blocking for Roller Shades

▶ SHOP DRAWINGS | Submittal Log

Glass Railing

Brake Metal

Main Stair Guard Rails

Wine

Millwork

Planters

Low Voltage

Louvers

Garage Door

Pedestals

# Item Submitted To By Owner Rep Decision Date Notes / Next Step
1.0 Plumbing — 2nd Floor Balancing Valves ($1.2K) CM PM ✅ APPROVED 5/4/2026 Verbal price approved.
2.0 Electrical — Specialty Outlets ($3.9K — Electrical Sub) CM PM ✅ APPROVED 5/4/2026 Approved by Owner Rep 5/4.
3.0 Electrical — Floor Boxes ($4.2K — Electrical Sub) CM PM ⚠ PARTIAL 5/4/2026 Approved EXCEPT wellness room. Reprice pending.
4.0 HVAC — Master Wing — no additional AC units Owner Rep APM/PM ✅ NO AC — CLOSED 5/4/2026 Decided by Owner Rep 5/4.
5.0 Shades — motorized massage room only PM/AV Vendor APM ✅ DECIDED 5/6/2026 Massage: motorized. Staff/baths: manual.
6.0 Foyer foam panels — run to floor, seal all sides Site Super/Interiors rep Interiors Co. ✅ DECIDED 5/6/2026 Interiors Co. confirmed. Instructions issued.
7.0 Stair Guard Rail CO CM PM ✅ APPROVED Prior Per PM's tracker.
8.0 Smart Glass Film CM PM ❌ REJECTED Prior Rejected per PM's tracker.
9.0 Baseboard Milling & Install CM PM ✅ APPROVED Prior Per PM's tracker.
10.0 Wine Unit — Ductless Slimline CM PM ✅ APPROVED Prior Per PM's tracker.
11.0 Metal Fencing & Enclosures ($531K) Owner Rep/CM PM ⏳ VE IN PROGRESS OAC5: CM issued instructions on sections. Final proposal from Fab Lead pending.
12.0 Interior Painting — Painting Sub Owner Rep APM/PM ✅ PRIMING APPROVED 5/13/2026 Interior priming approved OAC3. Painter mobilized.
13.0 Carousel — speed reduction gear upcharge Owner Rep PM ✅ UPCHARGE REJECTED 5/20/2026 Owner Rep rejected $3.2K + $750 upcharge at OAC4.
14.0 Civil Engineer Civil Eng — additional fees Owner Rep APM ⏳ PENDING Site Super sketch in progress to reduce scope.
15.0 Water Filtration — Culligan Owner Rep/CM PM ✅ DECIDED — OAC5 5/27/2026 RO to main kitchen faucet + $999 UV button upgrade. Owner Rep directed 5/27.
16.0 Wellness Center — Cryotherapy unit Owner Rep APM/MEP Eng ✅ DECIDED 5/20/2026 Owner Rep purchasing unit himself. Cryo Vendor directing conduit rough-in.
17.0 Gym Glass Wall (AGG Glass) CM / AGG Glass GC ⏳ SHOP DRAWINGS IN PROGRESS AGG Glass (Owner's contractor). Shop drawings in progress.
18.0 Safe Room Doors (~$1.5K/door) CM PM ⏳ COI PENDING ASAP GC office requested COI. Must verify insurance before routing to ownership.
19.0 Jib Doors — AC Mech Closets APM PM ⏳ APM TO REVIEW Two door types. APM reviewing.
20.0 AV Room HVAC APM PM ⏳ APM TO CLARIFY APM to determine exact equipment spec.
21.0 Millwork Installer for Millwork Co. APM / Site Super / Owner Rep PM ⏳ ON-SITE DISCUSSION APM and Site Super to discuss with Owner Rep directly.
22.0 Landscape Plans (Landscape Arch / LAND) Owner Rep APM ⏳ PENDING Post-recovery Landscape Arch had surgery. Sunshine 811 scheduled for marking then site walk.
23.0 Garage Cabinetry & Slat Walls (epoxy vendor) Interiors Co. / PM PM ⏳ INTERIORS WALKTHROUGH Decide during Interiors Co. walkthrough.
24.0 Shower Enclosures, Ribbed Glass & Mirrors APM / PM PM ⏳ PENDING CM no role. APM and PM manage.
25.0 Fire Feature — Galio Planika Fire Bowl Owner Rep GC ⏳ PENDING Purchase fire bowl. Fill slab below.
26.0 Dock Demo Owner Rep PM ⏳ PENDING Pending proposal from Shore.
27.0 Sheet Piles — Wall Gap Closure Owner Rep / PM PM ✅ APPROVED — OAC5 5/27/2026 PM sent proposal 5/26. Owner Rep approved at OAC5. Proceed immediately.
28.0 Veneer — Her closet / His & Her vanities / Massage / Cabana bar Owner Rep / Interiors Lead Interiors Co. ⏳ PENDING ⚠ TIME CRITICAL BEFORE 6/15 Must approve before June 15 Millwork Co. 2F delivery. Interiors Lead coordinating.
Bid Package/Description of Work Sub Contractor Buyout Status/Comments Awarded
Final Cleaning Proposals to be retrieved
Utility Easement There will be a cost to this scope for the Marina. Proposal previously submitted to be updated with new scope
Retaining Walls Facade Lead designing new scope. In AOR Court
Grading side & rear yards Onsite Removal of material/grading
Site Fencing the metal fabricator Facade Lead reviewing scope/PM making scope document so Owner Rep can get other proposal
Poured Concrete Driveway & Walkways RFPs sent to two subs
Landscaping, Irrigaton, Landscape Lighting Pending landscape design
Brake Metal the metal fabricator Review to capture all areas, verify color at front façade
Baseboard Testing Agency Proposal from Testing Agency provided, $13plf. Need to identify linear foot necessary and revise proposal
Millwork - Built-Ins, Vanities, Interior Doors, & Closets Millwork Co./the Architect Pending two jib doors at mech closet in chefs kitchen/mech closet. Pending wood ceiling at kitchen island
Interior Painting the painter or Painting Sub Pending interior paint proposal. the painter's received.
Repricing water Feature & Stone surround at door L-Gant Tile Pending proposal
Gym Flooring (Material & Install - Wood Plank & Wood Border) NWF Requesting additional planks for gym 2.
Wood Decking at Pool Deck the installer ? PM tracking down proposals for wood deck from the ceiling sub
Fire Feature Purchase of Galio Planika fire bowl - fill in slab below
Garage Cabinetry & Slat Walls epoxy vendor Design Needed from ownership, epoxy vendor Garage proposal needed
Shower Enclosures & Doors, Ribbed Glass, & Mirrors RFP's sent out on Friday. Sent to three fabricators
Plumbing Fixtures & Accessories Ferguson Complete flush plate purchase, garbage disposal push button, outdoor kitchen sink & faucet
Whole House Water Filter Circulate Proposals & leveling to ownership
Water Bug One proposal received — wireless option. AV Vendor providing alternate

🚧

ACTIVE WORK (ON SITE NOW)

(What should be happening / being pushed daily)

HVAC

Diffusers delivered → installation needs to be actively underway

Ceiling coordination tied directly to HVAC progress

Pushing manpower from HVAC Lead ⚠️

Electrical

Rough + ongoing electrical work progressing

Panel + routing coordination ongoing

Preparing for continued inspections

Framing / Interior Coordination

Framing dependent on:

Louver details from Facade Lead

Ceiling coordination (HVAC + lighting)

General Progress

Easy installation phase remaining (per your note)

Site should be in execution mode, not planning mode

BLOCKERS / ISSUES (STOPPING PROGRESS)

🚨 HVAC Manpower

HVAC Lead not providing enough workers

Diffusers on site but install not moving fast enough

→ Action: Letter escalation already required

🚨 Plumbing sub

Repeated no-shows

→ Formal notice required

→ Direct impact on inspections + progress

🚨 Gas Line (CRITICAL PATH)

TECO change not finalized:

3” low → 2” high pressure

→ Must be resolved before downstream work

🚨 Louver Details (Facade Lead)

Missing install details

→ Blocking framing progress

PENDING (NEEDS ACTION / FOLLOW-UP)

Proposals / Financial

Painters proposal

Interior flooring proposal

Exterior flooring proposal + layouts + submittals

Approvals

Owner approvals (create structured tracking)

Electrical revisions (Electrical Sub)

Gas system approval

Exterior finishes selections

Site / Utility

Mailbox location confirmation

Irrigation meter

Overflow pipe cleaning scheduling

Coordination

Transformer + panel location approval (the PE)

Responsibility

CM → payment for cameras

🔮

UPCOMING WORK (NEXT PHASES)

Flooring & Finishes

Finalize pavers (exterior)

Execute flooring installations

Painting scope execution

Exterior Scope

Finalize fencing → move to production

Determine boat dock removal + permits

Landscaping

Final landscaping plans

Resolve mango tree decision

Feature Elements

Glass railing execution

Water feature redesign (black granite / black stone)

🚨

CRITICAL PATH (TOP 6 DRIVERS)

(These control your schedule — everything else is secondary)

Gas line conversion (TECO)

HVAC manpower + diffuser install + ceilings

Plumbing sub reliability

Louver details → framing release

Electrical approvals (keep inspections moving)

Pending approvals (owner + subs)

🧠

SITE EXECUTION REALITY (IMPORTANT)

Right now your job is in a danger zone phase:

You have materials on site ✅

You have partial inspections passed ✅

But manpower + coordination gaps are slowing execution ⚠️

👉 This is where projects either:

Accelerate hard, or

Get stuck for weeks

🎯

WHAT YOU SHOULD BE PUSHING DAILY

If you strip everything down, your daily focus should be:

Force HVAC manpower onsite

Lock gas decision immediately

Push plumbing accountability

Get Facade Lead to release louver details

Keep electrical moving toward inspections

Eliminate any waiting on decisions

▶ APM'S MASTER TASK UPDATES | Rev 5/18/2026

GREEN = Done/Resolved | RED = Critical/Blocker | ORANGE = In Progress | PURPLE = New intel
#Category · Item · APM's Status (5/18) · Owner
1.0Exterior / Site · LED Metal Strip — galvanize · DONE · Site Super
2.0Civil · French Drain Relocation · DONE · Site Super
3.0Exterior · Foam Panel Finish — No painting · DONE — Decided no painting · Site Super/PM
4.0Civil / Structure · Piles — done and installed · DONE — the engineer will inspect slab steel · Site Super
5.0Exterior · Riglets — received full delivery, being installed · DONE — Delivery received, installation underway · Site Super
6.0Exterior / Site · NWF gym floor proposal · DONE and APPROVED · PM
7.0Permits · Garage door — NOA received · In progress — NOA got it, PM/APM preparing app · PM / APM
8.0Exterior · Spiral Stair & Railings — Fab Lead fabricating · Fab Lead starting fabrication 5/15 · Fab Lead / the metal fabricator
9.0Exterior / Civil · Transformer / Marina — easement complete · Easement complete and recording in process after owner signature · PM / Owner
10.0Permits · Condenser vibration isolators — ownership signature needed · Shops done by Mech Eng / EOR stamped. PM sent to Trust (Texas) 5/18 for signature. · Owner / PM
11.0Permits · MEP Revision — resubmitted 5/18 · PM/APM resubmitted to address comments 5/18 · PM / APM
12.0Permits · Building City inspector — front door slab/steps · Facade Lead meeting with building official to try to get approval. Engineer letter needed. · Facade Lead / APM
13.0Wellness / HVAC · Cryotherapy — new 208V unit + split condenser on roof (Owner Rep's supplier meeting 5/18 3pm) · Meeting with new cryo supplier from Owner Rep 5/18 at 3pm. 208V power and split condenser hidden on roof. · APM / Owner Rep
14.0Propane · Propane tank delivery — take delivery or storage charges begin · PM emailed asking to wait till mid-May, no reply. Will call — waiting to relocate dumpster. · PM / APM
15.0Permits · Window permit close-out — reprint stickers + sheetrock · After drywall — will need to reprint stickers and be sheet rocked · APM / Site Super
16.0Permits · Shearwall — re-engineering in wood (no pedestals, no NOA) · Struct Eng re-engineering in wood. Follow up 5/20. · Struct Eng / APM
17.0Framing · Chef kitchen AC — CM P does not want elevator shaft supplied by chef kitchen AC · Discuss with HVAC Lead at 5/6 walkthrough and get proposal · HVAC Lead / APM
18.02F — Finishes · Tile Sub Stone Sub — started measuring 5/15, 2F waterproofing/floor heating pads after drywall screw inspection · Stone Sub started measuring 5/15. Will commence 2F waterproofing + floor heating mud-in after drywall screw inspection. · Tile Sub / Site Super
19.02F — Finishes · Tile Lead tile — coming week of 5/18 to measure · Coming week of 5/18 to measure · Tile Lead
20.02F — Finishes · Painting Sub — start priming after drywall screw inspection (week of 5/18) · Painting Sub to start priming after drywall screw inspection 5/18 · Painting Sub / PM
21.0Exterior / Facade · Gas WH Electrical Conflict (vendor CO) — APPROVED, need electric work done · Approved — need electric work done · the vendor / APM
22.0Pool · Pool equipment — met Pool Tech 5/15, equipment coming in ~2 weeks · Met with Pool Tech 5/15. Equipment arriving in approximately 2 weeks. · Pool Tech / APM
23.0Exterior · Carousel — final price $3.2K parts + $750 install · APM called again. Final reduction: $3.2K parts / $750 install. Total $4.0K. · APM / PM
24.0Exterior · Garage Doors — cladding sequence discussion with Cladding Vendor · Discussed cladding install sequence with the cladding vendor. Waiting for vendor callback. · APM / Cladding Vendor rep
25.0Exterior / Civil · Driveways — leveling sheet being created · PM creating leveling sheet for 2 proposals. Need to confirm if included in city revision. · PM / APM
26.0Site / Civil · Pipe Work (City) — City rep visited 5/15 · City rep visited site 5/15. Owed proposal. Follow up 5/20. · APM
27.0Exterior · Fire Pit — PT wood structure. Proposal from the installer (Ceiling Sub) once Shearwall issues drawing · PT wood structure decided. Get proposal from Ceiling Sub once Shearwall drawing issued. · APM / Ceiling Sub
28.0Permits · Gas Tank — after delivery, approved revision needed to proceed · After delivery, need approved revision to proceed. MEP Eng working the revision. · MEP Eng / PM
29.0Electrical — 1F · Lighting Designer 1F electrical — says 3 weeks to complete · Lighting Designer says 3 weeks for 1F electrical completion. · Lighting Designer / APM
30.0Finishes · Wine display — sample wood needed before July delivery commit · Millwork Co. sending wood sample to approve then send to the millworker. Cannot commit to early July delivery without sample approval. · PM / APM
31.0Finishes · Millwork Co. — closed 5/18 holiday, discussing schedule 5/19 · Closed 5/18. Will discuss schedule with Millwork Co. rep on 5/19. · APM / Millwork Co. rep
32.0Finishes · Shower glass — PM sent latest RFP to APM · Go through all with Site Super. PM sent APM latest RFP. · APM / Site Super / PM
33.0Permits · Isolator shops — done, need Trust signature · Done by Mech Eng/EOR stamped. Need signed by ownership — PM sent to Texas (Trust) to sign. · Owner / PM
34.02F — Electrical · Top of elevator shaft — Lighting Designer needs detail. Light fixture? · Lighting Designer needs detail. Who buys fixture — Lighting Designer or GC? · Lighting Designer / APM
35.02F — Electrical · Wellness room — 208V power + split condenser (from Owner Rep cryo meeting) · Meeting 5/18 3pm with Owner Rep's cryo supplier. 208V unit + split condenser hidden on roof. · APM / Owner Rep / the PE
36.02F — Electrical · Remodel cans — wellness entry / VIP bedroom closet · Need spec from AV Vendor sent to Lighting Designer. PM to approve and order. · PM / AV Vendor / Lighting Designer
37.02F — Electrical · VPS ceiling cans for steam room (2 needed) · Site Super has materials and location. Will install. · Site Super
38.02F — Mechanical · Seal access panel back of elevator shaft · Site Super does not like current access panel. PM to order replacement. · PM / Site Super
39.02F — Mechanical · Water test all HVAC condensate drains in ceiling · Site Super to make plumber do it after drywall. Plumber should test all condensate drains. · Site Super / Plumber
40.01F — Mechanical · Transfer in laundry room — needs framing in hallway · HVAC Lead needs hallway framing. PM to check dimensions/markings then Site Super make framer do it. · PM / Site Super / Framer
41.01F — Mechanical · Framing for HVAC Lead office vestibule ceiling supply · 1F. Site Super to make framer do it. · Site Super / Framer
42.01F — Mechanical · China closet framing for supply box · 1F. Site Super to make framer do it. · Site Super / Framer
43.01F — Mechanical · Curved diffuser — HVAC Lead to deliver, coming 5/19 · They are on site. HVAC Lead coming 5/19. · HVAC Lead / Site Super
44.0Exterior / Stone · Brass bar inlay sample — Stone Sub needs to make carousel mockup · Brass bars coming. Ask PM — Stone Sub needs for carousel mockup. · PM / Stone Sub
45.0Exterior / Stone · Carousel mockup — Tile Sub checking for black slabs. Crack suppressant plan agreed. · Tile Sub agrees with Site Super's plan. Will add crack suppressant under tile. Company to inspect and own warranty. · Tile Sub / Site Super
46.0Finishes · Stucco punch list — APM/Site Super to walk and clean up · APM/Site Super walk stucco punch list and clean up. · APM / Site Super
47.0Finishes · Sill riser — waiting on higher gauge material from the supplier · the window vendor waiting on the supplier to receive higher gauge material. · the supplier / Window Vendor rep
48.0Finishes · El Gant — waiting for scaffold and wood to be moved for kickoff · El Gant coming for kickoff. Waiting for scaffold and wood to be moved. · Site Super / APM
49.0Finishes · Sconce spec near turntable — coordinate with Lighting Designer · Coordinate sconce spec near turntable wall with Lighting Designer. · Lighting Designer / APM
50.0Landscaping · Landscape Arch — surgery last week. Call after 5/20 for tree walk · Landscape Arch had surgery. Contact after 5/20 to schedule tree walk with Site Super re underground conflicts. · APM
51.0Permits · Stucco — APM/Site Super to walk punch list · APM/Site Super walk stucco punch list and stucco clean up. · APM / Site Super

▶ APM'S TASK LIST | Rev 5/18/2026

ItemAction · Responsibility note · Action

Second floor (PRIORITY WORK)

Electric-Lighting Designer

Top of elevator shaftLighting Designer needs detail · Lighting Designer owes light fixture? Or we buy?
Plan for additional equipment in Wellness roomMeeting with new Cryo supplier from Owner Rep 5/18 @3pm · 208 power and split condenser hidden on roof
Remodel cans in access panel Wellness entry/VIP Bdrm closetNeed Spec from AV Vendor sent to Lighting Designer · Need to approve spec · PM approve and order
Need 2 VPS ceiling cans for steam roomSite Super has materials and location will install
Final location chandelier up/down control switchConfirm with Lighting Designer · Inside AV closet
Steam Room LightingFinalize steam room lighting design. Confirm with ownership. AV VENDOR to set speaker in steam room ceiling (separate but coordinated). · Pending 2 speakers and 1 chromosome light

Mechanical-HVAC Lead

Seal access panel back of elevator shaftSite Super does not like the access panel we have · PM will order
water tast all in ceiling hvac condensate drainsSite Super make plumber/ · Site Super after drywall plumber should do it
Bedroom 2 damper blocking filter Fab Lead needs to change filter racks all ceiling AHU'sFab Lead changing filter racks

Plumbing- plumbing sub crew

Tub fillerHer master · Need jp to install
Tub drainHer master · Need jp to install
Anti scaldingHer master · Need jp to install
Balancing valvesCeiling outside master door · Need jp to install
Rain shower roughsNeed jp to install

LV AV Vendor LV Sub

steam room2 speakers and chromosome light

Bedroom 3 flip the keypad and thermostat

Finishes

Stone Tile SubStone Sub started measuring 5/15 and will commence second floor waterproofing/floor heating pads mud in/after drywall screw inspection second floor
Tile Lead tileComing week of 5/18 to measure
electricianSpecialty Outlets proposal · Done waiting on electrician to provide and install
Millwork Co.Millwork Co. rep · Closed for holiday on 5/18 will discuss schedule on 5/19
Master His & HerPaint Sub · Paint — Painting Sub start priming after drywall screw inspection 5/18
Master His & HerAV Vendor (unconfirmed) · Interiors Co. provides Id fixtures
NWFOwed us gym floor proposal · Done and approved
Shower glassGo thru all with Site Super · PM sent APM latest RFP
Wine displayNeeds sample wood before he can commit to early July delivery · Millwork Co. sending us wood sample to approve then send to the millworker

First Floor

Electric-Lighting Designer

Electrical — First Floor CompletionProvide completion date. Includes revised lighting plan + all relocations. ELD starting date 4/28. Blocks drywall close on first floor. · Lighting Designer says 3 weeks
turntable vendorProposal to Owner Rep — to install metal gear · APM called again - Final reduction they offered is $3.2K parts/ $750 install
Sconce spec for wall near turntableCoordinate with Lighting Designer

Mechanical-HVAC Lead

HVAC Lead first floor walk thruScheduled for 5/20
Transfer in laundry room 1 floorHVAC Lead says he needs framing hallway · PM check dimensions and markings then Site Super make framer do it
Framing for HVAC Lead office vestibule ceiling for supplyFirst floor · Site Super make framer do it
China closet framing in ceiling for supply box1 floor · Site Super make framer do it
CM P doesn't want the chef kitchen ac supplying the elev shaftDiscuss with HVAC Lead at 5/6 walkthru and get proposal$
Garage A/C RelocationUpdate plans for garage A/C relocation. Coordinate with mechanical drawings. · Discuss with HVAC Lead at 5/6 walkthru and get proposal$
Curved diffuserNeed from HVAC Lead · They are onsite HVAC Lead coming 5/19

Stone Systems MOCK UPS

Mock up brass bar inlay ? Need sample of brass barBrass bars coming? Ask PM as Stone Sub needs to make carosal mockup
Mockup the carouselTile Sub checking if he has black slabs for this · Tile Sub agrees with Site Super's plan and will add crack suppressant under tile and have crack suppressant company come inspect to own the warranty

Exterior/Facade/Sitework

Take delivery of propane tank or they will start charging us for storagePM emailed and asked to wait to mid May no reply · Will call them waiting to relocate dumpster
Fire pit redoGoing to be PT wood structure · Get a proposal from the installer once Shearwall issues drawing
Gas Water Heaters — Electrical ConflictRelocate underground electrical lines conflicting with gas line location. Proposal/CO pending from the vendor (~3 weeks). Requires owner approval to proceed. Status needed immediately. · approved need electric work done
Pool Equipment ReleaseRelease pool equipment to subcontractor to start. Pool pedestals, pool deck shop drawings, fire pit shop drawings all pending. · Met with Pool Tech on 5/15 equipment coming in approx 2 weeks
Transformer / Pedestals (Marina)Finalize pedestals and relocation plan. Coordinate with marina/utility provider. · Easement complete and recording in process after owner signature
Garage Doors ReleaseRelease garage doors for production. No further design holds — ready to issue. · Need to discuss cladding install sequence with the cladding vendor garage door guy - explained to garage door co & waiting for callback
Spiral Stair & RailingsRelease scope. Begin coordination. Proceed to installation. Coordinate with metal fabricator (metal fabricator / Fab Lead). · Fab Lead starting to fabricate 5/15
LED Metal Strip for stepsGalvanize. Approved on site. DEADLINE: 04/29/2026. Coordinate with the metal fabricator. · Done
Riglets — T&GPowder coating by Wednesday. Feeds exterior wood ceiling and baseboard reglet installation. · Received full delivery being installed
Pool AreaPool pedestals. Pool deck shop drawings. Fire pit shop drawings. Coordinate with pool equipment release. · Waiting on Shearwall to re engineer no pedestals
Retaining Wall (Public Works)Finalize solution for retaining wall with Public Works. Coordinate with civil. · Sheet piles approved by city/PM will send proposal to CM for approval
Roof — Metal Equipment EnclosureShop drawings → fabrication → installation sequence. Coordinate with metal fabricator and roofing. · Included in the metal fabricator fencing quote under review. Not a separate CM approval — part of overall fencing scope decision.
French Drain civil RelocationScheduled for Thursday. Check required — confirm contractor mobilized and work proceeding. · Done
Gas Tank CoordinationCoordinate gas tank installation with propane delivery, survey, and civil work. · After delivery need approved revision to proceed / MEP Eng is working the revision
Pipe Work (City)Clean pipe — no lining. Coordinate with city. Likely related to French drain / civil scope. · City rep visited site 5/15 owed proposal follow up 5/20
Foam Panel SubFluted foam panels — stone vs. painted DECISION NEEDED · Decided no painting · Installation completion target · 5/31/2026
DrivewaysDecide between 2 proposals · PM creating leveling sheet · Need to see if included in current revision being processed at city
Pile Contractor propane tankInspection + 10-day mobilization lead · Piles done and installed · the engineer will inspect when he inspects slab steel
Stuccothe stucco sub · APM/Site Super walk stucco punch list and stucco clean up
the window vendor — Window Vendor repSill riser issue · Waiting on the supplier to receive higher gage material
El Gant coming for kickoffWaiting for scaffold and wood to be moved
LandscapingLandscape Arch has surgery last week call after 5/20 to schedule tree walk with Site Super re: underground conflicts
Water meter /gas meterAPM will follow up

Roof

Condenser vibration isolatorsengineering prepping design for stands · Shops received from Mech Eng/stamped by EOR · Waiting for ownership to sign permit app PM sent to Trust on 5/18

Permitting

******Building inspector needs to see evidence of inspecting front door new slab and steps that got pouredMet with inspector need to recall inspection of front stairs and at grade landing slab, have engineer letter when he comes · Facade Lead meeting with Bld Official to try to get approval
MEP REVISONPM/APM already resubmitted to address comments on 5/18
File front doorCladding Vendor to provide NOA · Still pending NOA fromCladding Vendor
File garage doorIn progress · PM/APM preparing app we got the NOA
Close out window permitWe will need to reprint stickers and be sheet rocked · After drywall
Shearwall is engineering pedestals for exterior wood deckNo pedestals no NOA · Manual re engineering in wood follow up 5/20
Isolators shopsDone by Mech Eng/Stamped by EOR · Need signed by ownership PM sent to Texas for the Trust to sign

▶ MASTER TASK LIST | Site Task Log

Second floor (PRIORITY WORK TO DRYWALL)

Electric-Lighting Designer

list from 4/28 walk thruLighting Designer says done by 5/1
Master headboard sconcescall Garde re mounting detail · APM · X
Top of elevator shaftLighting Designer needs detail · Lighting Designer owes light fixture
Plan for additional equipment in Wellness roomMEP consultant sending comments also on this 5/6 · MEP Eng will follow up with the PE and discuss next OAC2
Remodel cans in access panel Wellness entry/VIP Bdrm closetNeed Spec from AV Vendor sent to Lighting Designer · Need to approve spec · PM approve and order
Need 2 VPS ceiling cans for steam roomMight be on site · APM tell Lighting Designer/Site Super will babysit layout · Site Super make Lighting Designer install
Final location chandelier up/down control switchConfirm with Lighting Designer · Inside AV closet
Lighting Designer needs exterior sconce locations marked outside massage room balconyCheck plans and have Site Super mark wall · APM · X done except low one on side of walkway
Steam Room LightingFinalize steam room lighting design. Confirm with ownership. AV VENDOR to set speaker in steam room ceiling (separate but coordinated). · X
Master bath floor heaterCheck out control trim and how does heater meet window/floor thickness? · Site Super is going to examine it to confirm how it works against sill
Elevator smoke detectorMove to center line hallway in line with other smoke detector

Mechanical-HVAC Lead

HVAC — Supply Duct FailureSend demand letter to HVAC Lead. Supply ducts at plenums are coming apart. Immediate correction required. No response → escalate with the engineer.-HVAC Lead says done by Friday 5/1 walk job with HVAC Lead on Wednesday 5/6 · Completed walk thru of second floor with HVAC Lead -Site Super working on remaining open items on second floor
Pre drywall walk thruScheduled with HVAC Lead for wed 5/6 10am · Done 5 6
Freon lines in master mech closet need to be loweredNeed to tell HVAC Lead · Told HVAC Lead at walkthru
Insulate all horizontal condensate linesSite Super make HVAC Lead do it/extra material arrives 4/30 · Site Super/materials are here 5/1
remote ac sensors? in master and gymHVAC Lead will do · We gave locations to HVAC Lead at walkthru
All fresh air dampers installed and working?HVAC Lead says yes 5/6 · Confirmed with HVAC Lead at walkthru
Seal access panel back of elevator shaftSite Super does not like the access panel we have · Site Super will order one that seals/lock or no lock?confirm lock with PM before order
Return for mech closet in guest bed 1Try to get the PE M engineer to agree with return from corridor · the PE approved/ Site Super says in progress and has all materials/ needs to draw from hallway Plenum also per the engineer
water tast all in ceiling hvac condensate drainsSite Super make plumber/ · Site Super after drywall plumber should do it
make return from guest bed#1 to corridorthe PE approved and in progress/sent photos to the PE · Site Super in progress
HVAC — Master WingFinal decision required. Requires owner approval before HVAC sub can proceed in master wing. Plenum in master hallway and gym also flagged 'Hot' on board. · Not adding additional unit for master
Bedroom 1 drain blocking filter - HVAC LeadResults of 5/6 walkthru w/HVAC Lead
Relocate access panel bedroom 1 & bedroom 3- HVAC LeadResults of 5/6 walkthru w/HVAC Lead
VIP suite needs slot for filter from Fab LeadResults of 5/6 walkthru w/HVAC Lead
Bedroom 2 damper blocking filter Fab Lead needs to change filter racks all ceiling AHU'sResults of 5/6 walkthru w/HVAC Lead

Plumbing- plumbing sub crew

Tub fillerHer master · Site Super will core drill and have have plumber install rough in floor
Tub drainHer master · Site Super will core drill and have have plumber install rough in floor
Anti scaldingHer master · Plumber asking inspector Site Super tell plumber we need one only has one valve/PM sending detail of device anti scald to Site Super · Plumber says we need it and he will find a spot after the rough is in the floor
Balancing valvesCeiling outside master door · After core drill Plumber will locate a spot for it · ✅ APPROVED by Owner Rep 5/4/2026 · Approved — written proposal to be resubmitted for file
Water supply line massage room to highSite Super tell plumber

Rain shower roughs

LV AV Vendor LV Sub

Did walk thru with LV Sub 4/29LV Sub says target is Friday 5/1
PM / AV SubAV Change Order — confirm + process · PM thinks no
AV VENDORShade wire (dressing room) + alarm boxes + steam room speaker · Pre drywall check LV Sub work list
Does LV Sub instal steam room speakersSite Super ask him

Bedroom 3 flip the keypad and thermostat

Finishes

His & Hers Bathroom Stone — Delivery ScheduleProvide date schedule for delivery to fabricator. Tile Sub Stone process: Material → Digital Layout → Cut → Install. Backing date and vanity L-angles also TBD (flagged red on board). · GC wants list of which bathrooms/areas get stone first to start shop drawings · PM make list of Second floor slab areas and email GC/APM list
electricianSpecialty Outlets proposal · Done waiting on electrician to provide and install
Millwork Co.Millwork Co. rep · Owner Rep asking for delivery target date · PM contact Millwork Co. and discuss phased delivery
Master His & HerPaint Sub · Paint — master suites waiting for the painter proposal
Master His & HerAV Vendor (unconfirmed) · Interiors Co. provides Id fixtures
NWFOwed us gym floor proposal · PM follow up

First Floor

Electric-Lighting Designer

Electrical — First Floor CompletionProvide completion date. Includes revised lighting plan + all relocations. ELD starting date 4/28. Blocks drywall close on first floor. · After Lighting Designer finishes 2nd floor Site Super meets with Lighting Designer for first floor schedule and needs
turntable vendorProposal to Owner Rep — to install metal gear · They reduced installation price but Owner Rep wants us to push back and get credit for gear being removed

Mechanical-HVAC Lead

HVAC Lead first floor walk thruScheduled for 5/20
Transfer in laundry room 1 floorHVAC Lead says he needs framing hallway · PM check dimensions and markings then Site Super make framer do it
Framing for HVAC Lead office vestibule ceiling for supplyFirst floor · Site Super make framer do it
China closet framing in ceiling for supply box1 floor · Site Super make framer do it
CM P doesn't want the chef kitchen ac supplying the elev shaftDiscuss with HVAC Lead at 5/6 walkthru and get proposal$
Garage A/C RelocationUpdate plans for garage A/C relocation. Coordinate with mechanical drawings. · Discuss with HVAC Lead at 5/6 walkthru and get proposal$

Stone Systems MOCK UPS

Mock up brass bar inlay ? Need sample of brass barBrass bars coming 5/8
Mockup the carouselPM calling the stone supplier for some material Black Infinity Leathered

Exterior/Facade/Sitework

Take delivery of propane tank or they will start charging us for storagePM emailed and asked to wait to mid May no reply · Call by 5/15 and tell to deliver /Site Super clear area and prep for delivery
Fire pit redoWood or concrete need to decide · Get a proposal from the installer for wood — pool sub owes a proposal
Gas Water Heaters — Electrical ConflictRelocate underground electrical lines conflicting with gas line location. Proposal/CO pending from the vendor (~3 weeks). Requires owner approval to proceed. Status needed immediately. · approved need electric work done
Pool Equipment ReleaseRelease pool equipment to subcontractor to start. Pool pedestals, pool deck shop drawings, fire pit shop drawings all pending. · Invoice has been submitted to accounting, pending payment to commence work
Transformer / Pedestals (Marina)Finalize pedestals and relocation plan. Coordinate with marina/utility provider. · Surveyor preparing easement for recording by 5/6 folow up
Garage Doors ReleaseRelease garage doors for production. No further design holds — ready to issue. · Need to discuss cladding install sequence with the cladding vendor
Spiral Stair & RailingsRelease scope. Begin coordination. Proceed to installation. Coordinate with metal fabricator (metal fabricator / Fab Lead). · Fab Lead should be starting to fabricate Site Super confirm with Fab Lead he started to fab
LED Metal Strip for stepsGalvanize. Approved on site. DEADLINE: 04/29/2026. Coordinate with the metal fabricator. · Done
Riglets — T&GPowder coating by Wednesday. Feeds exterior wood ceiling and baseboard reglet installation. · Received partial deliver 5/1 · The window vendor is onsite cutting windows for ringlets 5/7
Pool AreaPool pedestals. Pool deck shop drawings. Fire pit shop drawings. Coordinate with pool equipment release. · Send the the engineer markups to Shesrwall · PM/APM
Retaining Wall (Public Works)Finalize solution for retaining wall with Public Works. Coordinate with civil. · Ball in Facade Lead court to provide engineering detail
Roof — Metal Equipment EnclosureShop drawings → fabrication → installation sequence. Coordinate with metal fabricator and roofing. · Included in the metal fabricator fencing quote under review. Not a separate CM approval — part of overall fencing scope decision.
French Drain civil RelocationScheduled for Thursday. Check required — confirm contractor mobilized and work proceeding. · Done
Gas Tank CoordinationCoordinate gas tank installation with propane delivery, survey, and civil work. · After delivery need approved revision to proceed / MEP Eng is working the revision
Pipe Work (City)Clean pipe — no lining. Coordinate with city. Likely related to French drain / civil scope. · Follow up with city pipe cleaning sub then Site Super will camera it
Foam Panel SubFluted foam panels — stone vs. painted DECISION NEEDED · Decided no painting · Installation completion · 5/31/2026
DrivewaysGetting proposal
Pile Contractor propane tankInspection + 10-day mobilization lead · Scheduled for 5/11 pending approved revision that the designer is working on
Stuccothe stucco sub · APM/Site Super walk stucco punch list and stucco clean up
the window vendor — Window Vendor repSill riser issue · Conflict - RAUL saying he can provide new risers at no charge that snap on but Site Super thinks you have to rip out sills to install and we need the new sills that snap on from infinite - need to sort this out asap
Site Super list of details front entrance facadeSite Super gave APM photo with list of details needed
Main house transformer can it oriente it E/W and make gate on the insideDiscussed with Owner Rep - will try to hide with landscaping , doubt follow allows it to change

El Gant coming on 5/15 for kickoff

Roof

Condenser vibration isolatorsThe engineering team prepping design for stands · Follow up 5/6
Site Super and APM walk roof make listWeek of 5/4

Permitting

******Building inspector needs to see evidence of inspecting front door new slab and steps that got pouredMet with inspector need to recall inspection of front stairs and at grade landing slab, have engineer letter when he comes · Site Super getting letter from S engineer EOR
Gas Revision (Life Safety)Finalize gas revision. Cannot close walls until completed. Required for final sign-off on life safety inspection. · Pending resvion from MEP Eng
File front doorCladding Vendor to provide NOA
File garage doorGet NOA from door vendor, then finish inspection
Close out window permitWe will need to reprint stickers and be sheet rocked · After drywall
Shearwall is engineering pedestals for exterior wood deckSent comments to shearwall 5/1 · Need to process a shop drawing for the pedestals

▶ PM'S TRACKER

Construction Items In ProgressStatus/Date · Notes

Mechanical

Hood drop at Chefs KitchenUnderway · SE Mechanical
Hood Drop at main kitchenUnderway · SE Mechanical
Wine Unit RefrigerationUnderway · Pending approval to upcharge for slim line unit · SE Mechanical
AV Room CoolerUnderway · Reverting to dedicated AC unit · SE Mechanical
Pressurize system to indentify leaksUnderway · SE Mechanical
Garage Mini SplitsUnderway · Pending locations/drain/plywood blocking · SE Mechanical
Connect condensate drainsUnderway · SE Mechanical

Metals

Interior LouversPending · Shops/ Design update with Facade Lead · Metal Fabricator
Stucco & Knife Edge WorkUnderway · Metal Fabricator
Bracket for Gym WindowUnderway · Metal Fabricator
GC/Interiors Co.Laying out FFE & Millwork · Underway
Blocking for TVsUnderway
Blocking for Roller ShadesUnderway

Framing

Framing for pocket doors at New GymUnderway · Door Vendor

Millwork

Vanity Support Locations - QuantityUnderway · APM O to provide locations/GC to install · Millwork Co.
Millwork Co. Phase 1 Millwork Shops ApprovedSD's Approved · In Fabrication · Millwork Co.
Millwork Co. Phase 2 (Holding Laundry until plumbing complete)Underway · Millwork Co.
the Architect Millwork Shop Drawings ApprovedSD's Approved · In fabrication · the Architect

Electric

Complete Light Fixture Rough & Outlet RoughUnderway · Electrical Sub
Complete Panel InstallationUnderway · Electrical Sub

Low Voltage

Steam Speaker & Light RoughUnderway · AV Vendor
Complete wiringUnderway · AV Vendor

Finishes

Floor Floating/ LevelingUnderway · NWF
Exterior Tongue & Groove CeilingsUnderway · Ceiling Sub
Paint Samples at ExteriorUnderway · Stucco Sub

Plumbing

Plumbing -copper, shower pansUnderway · Plumbing sub
Plumbing InsulationUnderway · Plumbing sub
Her Master Bath Tub Filler Rough & Tub DrainUnderway · Plumbing sub
Steam rough completion (aroma)Underway · Plumbing sub

Propane Tank

Scaffold RemovalPending
Drive the (4) Helical PilesPending
Slab PourPending
Deliver/ Set/Pipe in TanksPending

Milestone Deliverables

Stone Deliveries05/01/2026
ID LightingTBD
MillworkTBD · Getting schedule from fabricators
Entry Pivot Door10/01/2026
Wood Flooring07/01/2026 · Expecting Arrival End of July
Wine Wall Display07/01/2026

Ownership Items - Change Orders to Review

Stair Guard RailPending · Pending ownership approval · Approved
Smart Glass FilmPending · Pending ownership approval · Rejected
Baseboard Milling & InstallPending · Pending ownership approval · Approved
Swing Doors for Chefs KitchenPending · Pending ownership approval
AV Room HVACPending · Pending ownership approval
Wine Unit - Ductless SlimlinePending · Pending ownership approval · Approved
Interior PaintingPending · Pending ownership approval
Millwork Installer for Millwork Co.Pending · Pending ownership approval

Shop Drawings/ Specialty Engineering

Revising Shoe & Glass Rail PackageIn Progress · New plans being issued 4/10-then counter sign & submit · Electrical Sub Eng
Creating engineered shop drawing for elevated condensersIn Progress · Retaining the engineering team Design to create SK & Provide Letter · the engineering team
Modifying exterior column framingIn Progress · With bigger frames to go past concrete · Shearwall
Deck design with pedestalsIn Progress · Shearwall

Permits

Shop Drawings/ NOA Needed for Permit for front doorPending
Shop Drawing/NOA for Garage DoorPending
Deck design with pedestalsIn Progress · Shearwall

Inspections

Low VoltagePassed · AV Vendor
Windows Buck- AnchoringPassed · Window Vendor
Roof In ProgressPassed · inspector
Mechanical RoughPassed · SE Mechanical
Fire Alarm Rough InspectionPassed · Electrical Sub
Framing Rough InspectionPassed · Passed except for Staff Area/Service Wing · GC
Gas RoughTBD · Pending Approvals on MEP Revision · Plumbing sub
Electrical RoughPartials · Pending Ground Floor & Garage · Electrical Sub
Plumbing Rough (shower pans & insulation to be inspected)TBD · Gym & Master Showerpans/Pipe insulation · Plumbing sub
Insulation InspectionTBD · To Be scheduled after Icynene & again after exterior walls

Design Items

Architecture

Site plan of marina for easement recording for FPLIn Progress

Structure

Ongoing Review of shop drawings for permitsIn Progress

Vendor

Adjust their recommendations for sconditions in fieldIn Progress

Interior

Master Carpet Specification
FFE Layout with Owner
Fabrics & Veneers Final Schedule
Exterior Ceiling Fans

Lighting

AV Vendor adding in missing addresses for the millworkIn Progress · AV Vendor

Landscape

Pending new plans from the landscape firmNeed Update · Landscape Arch
Landscape LightingNeed Update · Landscape Arch?

MEP

Submittal of Hot Water HeaterPending Review · In MEP Court · MEP
Submittal for AC RoomPending Review · In MEP Court · MEP
Submittal for Wine Wall RefrigerationPending Review · In MEP Court · MEP
Narrative to Resolve Revision Denial CommentsNeed Update · MEP Eng working with MEP · MEP
Submittal for Balancing ValvesIn Progress · Facade Lead Reviewing with MEP · MEP
Wellness Equipment ElectricalIn Progress · MEP
Buyouts Section - General to be Sub ContractedStatus · Notes · Contractor
Stair Guard RailIn Progress · New proposal submitted for painted metal finish · Metal Fabricator
Driveway, Pedestrian, Side Yard Gates, HandrailsIn Progress · Re-pricing · Metal Fabricator
Wine Room InstallerIn Progress · Submitted Proposal, GC to retrieve additional
Water Feature StoneIn Progress · Pending Proposal/ Upgrade Insurance · L-Gant
Stone surround at entryIn Progress · Pending Proposal/ Upgrade Insurance · L-Gant
Deck & Pedestal SystemIn Progress · Testing Agency Submitted, Pending reviewer sign-off · Testing Agency
Garage DoorsIn Progress · Garage Door Co. Approved with Vertical Cedar · Garage Door Co.
Garage Cabinetry & FlooringIn Progress · Proposal to be retrieved · epoxy vendor
LandscapingIn Progress · Pending New Plans
Landscape LightingNeed Update · Pending Design
IrrigationIn Progress · Pending New Plans
Shower EnclosuresIn Progress · Pricing
Driveways & WalkwaysIn Progress · Re-pricing, New design with concrete & turf · Miami Crete
Interior PaintingIn Progress · Proposals submitted · the painter or Painting Sub
New Gym Rubber FlooringIn Progress · Requested pricing from NWF · NWF
Walnut Veneer at Kitchen Island CeilingIn Progress · Requested pricing from Millwork Co. · Millwork Co.
Wellness EquipmentIn Progress · Requested pricing from Electrical Sub · Electrical Sub
In floor heating for His & Her Master

Issues to Resolve

Speed of the Car Carousel
Dock DemoPending Proposal & Review Process · Shore
Schedule Critical PathStatus/Date
Completion DateTCO & Move In: · 08/01/2027
CO12/31/2027

▶ PENDING MATERIALS | Long-Lead + Owner Hot Items

HOT ITEM — OWNER KEEPS ASKING ABOUT

-powder coated ringlets expected on 5/1

-Target delivery date for millwork Millwork Co. (We need to look into phased delivery? Is this practical or even possible?)

HVAC

Diffusers (verify full delivery vs. partial)

Plenum boxes (especially foyer curved diffusers)

Linear slots / specialty ceiling vents

Mini-split units (if any still outstanding)

Grilles and return covers

Electrical

Light fixtures (interior + exterior)

LED step lights (magnetic – per your preference)

Panels / breakers (if revisions still pending approval)

Exterior lighting + landscape lighting

Low-voltage components (cameras, wiring, devices)

Plumbing

Fixtures (toilets, faucets, specialty items)

Water heaters / equipment

Exterior hose bibs / drainage components

Pipe materials for remaining rough/finish

Gas

Propane tank (new installation – critical path)

Gas piping materials (2” high-pressure conversion)

Regulators + fittings

Architectural / Finishes

Interior floor finishes (pending proposal + selection)

Exterior pavers (still needs confirmation)

Stucco materials / finish coats

Paint system (Loxon primer confirmed, but full system?)

Caulking (caulking sub for finish transitions)

Millwork / Specialty

Wine display systems

Custom cabinetry

Interior doors / hardware

Security doors

Exterior / Site

Fencing (final decision pending)

Mailbox

Irrigation system materials + meter

Landscaping materials (pending plans + mango tree decision)

Structural / Misc

Louvers (awaiting Facade Lead details)

Framing-related specialty items tied to louvers

Glass railings (proposal needs execution)

Water feature materials (black granite revision)

▶ MANPOWER LOG | May 11–18, 2026

✅ DRYWALL SCREW INSPECTION PASSED 5/18 (ENTIRE 2ND FLOOR) | Door Vendor adding 10 finishers 5/19 | 1F drywall starts 5/19
DateCompany · # Workers · # Hours · Man-Hours · Work Performed / Notes

Monday, May 11, 2026 | 51 workers | 10 trades

05/11/2026Door Vendor Drywall · 14.0 · 8.0 · 112 · Hanging Drywall / Finishing coves / installing Dorr houzzer Framing Luver area
General Contractor6.0 · 8.0 · 48 · - Site Super Superintendent - APM - Labor
Natural Wood Flooring6.0 · 8.0 · 48 · Plywood installation fist floor
Electrical Sub5.0 · 8.0 · 40 · Electrical lights panel
Architectural Pre Cast & Foam5.0 · 8.0 · 40 · Foam installation
the stucco sub.5.0 · 8.0 · 40 · Painter
the metal fabricator4.0 · 8.0 · 32 · - Shoe inspection Pass. - Rooftop parapet cover replace.
Ceiling Sub3.0 · 8.0 · 24 · T&G kitchen area
the stucco sub.2.0 · 8.0 · 16 · Stucco punch out
HVAC sub1.0 · 8.0 · 8 · Punch out

Tuesday, May 12, 2026 | 55 workers | 11 trades

05/12/2026Door Vendor Drywall · 15.0 · 8.0 · 120 · - Drywall Lead on site most of the day - Hanging Drywall / Finishing coves / - installing Dorr houzzer - Framing Luver area - T&G Riglet installation
Pool Sub Group7.0 · 8.0 · 56 · -Electrical sub supervisor was on site most of the day supervising. - Pile installation - Removing forms from the front steps
General Contractor6.0 · 8.0 · 48 · - Site Super Superintendent - APM - Labor
Natural Wood Flooring6.0 · 8.0 · 48 · Plywood installation VIP, kids# 2-3
Electrical Sub5.0 · 8.0 · 40 · Electrical panel electrician couple hours Lighting Designer most of the day
Architectural Pre Cast & Foam5.0 · 8.0 · 40 · Foam installation
the stucco sub.3.0 · 8.0 · 24 · Painter caulking windows
Ceiling Sub3.0 · 8.0 · 24 · T&G kitchen area
the stucco sub.2.0 · 8.0 · 16 · Stucco punch out
Facade Lead Architects + Associates2.0 · 2.0 · 4 · MEP Eng’s Facade Lead
HVAC sub1.0 · 8.0 · 8 · Punch out

Wednesday, May 13, 2026 | 46 workers | 9 trades

05/13/2026Door Vendor Drywall · 15.0 · 8.0 · 120 · - Drywall Lead on site most of the day - Hanging Drywall / Finishing coves / - installing Dorr houzzer - Framing Luver area - T&G Riglet installation
General Contractor6.0 · 8.0 · 48 · - Site Super Superintendent - APM - Labor
Natural Wood Flooring6.0 · 8.0 · 48 · Plywood installation gym wellness
Architectural Pre Cast & Foam5.0 · 8.0 · 40 · Foam installation
the stucco sub.4.0 · 8.0 · 32 · - Removing scaffolding - Punch out
Electrical Sub3.0 · 8.0 · 24 · Electrical panels
Ceiling Sub3.0 · 8.0 · 24 · T&G kitchen area
the stucco sub.2.0 · 8.0 · 16 · Painter caulking windows
Pool Sub Group2.0 · 8.0 · 16 · - Removing forms from the front steps

Thursday, May 14, 2026 | 53 workers | 11 trades

05/14/2026Door Vendor Drywall · 16.0 · 8.0 · 128 · - Hanging Drywall / Finishing coves - installing Dorr houzzer - Framing Luver area - T&G Riglet installation
General Contractor6.0 · 8.0 · 48 · - Site Super Superintendent - APM - Labor
Natural Wood Flooring6.0 · 8.0 · 48 · Plywood installation gym wellness
Electrical Sub5.0 · 8.0 · 40 · Electrical panels
Architectural Pre Cast & Foam5.0 · 8.0 · 40 · Foam installation
the metal fabricator4.0 · 8.0 · 32 · Mainstairs mockup
the stucco sub.3.0 · 8.0 · 24 · - Removing scaffolding - Punch out
Ceiling Sub3.0 · 8.0 · 24 · T&G kitchen area
the stucco sub.2.0 · 8.0 · 16 · Painter caulking windows
JAJ INSULATION CORP.2.0 · 8.0 · 16 · Punch out
the Architect1.0 · 8.0 · 8 · Carpenter installing 1/4 Birch plywood

Friday, May 15, 2026 | 56 workers | 11 trades

05/15/2026Door Vendor Drywall · 16.0 · 8.0 · 128 · - Hanging Drywall / Finishing coves - installing Dorr houzzer - Framing Luver area - T&G Riglet installation
General Contractor6.0 · 8.0 · 48 · - Site Super Superintendent - APM - Labor
Natural Wood Flooring6.0 · 8.0 · 48 · Plywood installation gym wellness
Electrical Sub5.0 · 8.0 · 40 · Electrical outlets
Architectural Pre Cast & Foam5.0 · 8.0 · 40 · Foam installation
the metal fabricator4.0 · 8.0 · 32 · Mainstairs mockup
Pool Equipment Sub4.0 · 8.0 · 32 · - Installing Jandy panels - water feature relocating waterlines under the finish grade
the stucco sub.3.0 · 8.0 · 24 · Painting metal riglet transitions throughout the knife edge
the stucco sub.3.0 · 8.0 · 24 · - Removing scaffolding - Punch out
Ceiling Sub3.0 · 8.0 · 24 · T&G kitchen area
the Architect1.0 · 8.0 · 8 · Carpenter installing 1/4 Birch plywood
Monday, May 18, 2026 | 48 workers | 10 trades ★ DRYWALL SCREW INSPECTION PASSED — 2F COMPLETE
05/18/2026Door Vendor Drywall · 14.0 · 8.0 · 112 · - Hanging Drywall / Finishing coves - installing Dorr houzzer - Framing Luver area - T&G Riglet installation
General Contractor6.0 · 8.0 · 48 · - Site Super Superintendent - APM - Labor
Natural Wood Flooring6.0 · 8.0 · 48 · Plywood installation gym wellness
Electrical Sub5.0 · 8.0 · 40 · Electrical
Architectural Pre Cast & Foam5.0 · 8.0 · 40 · Foam installation
the stucco sub.3.0 · 8.0 · 24 · Painting metal riglet transitions throughout the knife edge
the stucco sub.3.0 · 8.0 · 24 · - Removing scaffolding - Punch out
Ceiling Sub3.0 · 8.0 · 24 · T&G máster bedroom patio
Pool Equipment Sub2.0 · 8.0 · 16 · - Installing Jandy panels - water feature relocating waterlines under the finish grade
the Architect1.0 · 8.0 · 8 · Carpenter installing 1/4 Birch plywood door guides

CM INTELLIGENCE FLAGS — MAY 11–18, 2026

★ MILESTONE✅ DRYWALL SCREW INSPECTION PASSED — ENTIRE 2ND FLOOR — 5/18/2026 · Critical path milestone achieved. Door Vendor adding 10 finishers 5/19. 1F drywall installation starts 5/19. Backing installation begins on one side throughout entire 1F. Significant manpower increase incoming. This is the project's most important milestone since piles were installed.
✅ POSITIVEDoor Vendor Drywall — ramping to record levels. 14→16 workers, adding 10 finishers 5/19 · Consistently 14-16 workers across all 6 days. Now expanding to include finishers. MEP Eng on site 5/12 and 5/13. 1F start 5/19 is a major acceleration signal.
✅ POSITIVEthe metal fabricator — Main Stairs mockup 5/14 and 5/15 · Main stairs mockup underway per OAC3 direction. 4 workers both days. Fabrication scope progressing.
✅ POSITIVEPool Equipment Sub — Jandy panels and water feature line relocation (5/15 + 5/18) · Pool Equipment Sub appeared 5/15 (4 workers) and 5/18 (2 workers) installing Jandy panels and relocating water feature waterlines. Active pool/water feature scope progressing.
✅ POSITIVEthe Architect — Carpenter on site 5/14, 5/15, 5/18 installing door guides · 1 worker installing 1/4 birch plywood door guides. Consistent presence. Interior millwork prep underway.
✅ POSITIVEPool Sub Group — forms removed from front steps 5/13 · Forms removed from front steps. Structural concrete work progressing. Also supervisory role confirmed.
✅ POSITIVEthe stucco sub — painting metal riglet transitions at knife edge (5/15 + 5/18) · Riglets being painted at knife edge. Scaffold removal also ongoing. Exterior finishing sequence advancing.
✅ POSITIVECeiling Sub — expanded to master bedroom patio area 5/18 · Previously T&G kitchen. Now also master bedroom patio. Scope expanding — confirms Ceiling Sub's reliability for broader exterior wood ceiling scope.
🔴 CRITICALPlumbing sub — ABSENT ALL 6 DAYS (5/11 through 5/18) · Not a single day logged over the full 6-day period. Drywall screw inspection is now passed — ceiling closure sequence is starting. If the plumbing sub does not appear to complete and test condensate drains and tub/shower roughs before ceilings close, those items get drywalled in. Demand letter is now urgent at the highest level.
🔴 CRITICALHVAC sub — 1 person, 2 of 6 days only (5/11 + 5/12), absent 5/13–5/18 · Present only 5/11 and 5/12 for punch out. Completely absent 5/13 through 5/18 — a 6-day consecutive absence during the week ceiling closure begins. HVAC punch list items from the 5/6 walkthrough (bed 1 drain, access panels, VIP filter slot, bed 2 damper racks) are still open. If HVAC Lead does not clear these before Door Vendor closes 1F ceilings, they are permanently inaccessible.
📋 NOTEJAJ Insulation Corp — 2 workers 5/14 for punch out · One-time appearance for insulation punch out. Not new scope — cleanup work.
📋 NOTEthe Architect — 'Carpenter' appearing consistently (5/14, 5/15, 5/18) · Not previously in any tracker under this name. Installing 1/4 birch plywood — likely door guide prep work. Confirm sub relationship and whether this is a CO or base scope.

▶ BOARD LOG | 5/13/2026

DONE | NEW | RED = Critical | -> = Reassigned

#Trade · Sub / Vendor · Action Item · Target Date · Status · Priority · Board Change (5/13)
1.0Roofing · Roofing Sub · Scaffolding removal · 5/4-5/5 · DONE · HIGH · CROSSED OUT — done 5/4 or 5/5
2.0Roofing · the metal fabricator · Rooftop parapet cap replacement — completed 5/6 · 5/6/2026 · DONE · HIGH · Completed per board + manpower log confirmed
3.0Roofing · Roofing Sub · Overflow scuppers caught back · 5/11/2026 · DONE · HIGH · 'Caught back the overflow scuppers 5/11' on board
4.0Roofing · Roofing Sub · Waterproofing punch out areas · 5/11/2026 · DONE · HIGH · 'Continue waterproofing punch out areas 5/11' on board
5.0Roofing · HVAC sub · Isolations — HVAC Lead confirmed done · 5/11/2026 · DONE · HIGH · 'I HVAC Lead' CROSSED OUT — isolations confirmed complete
6.0Roofing · the stucco sub. · Stucco shoe rooftop · 5/14/2026 · DONE · HIGH · 'Stucco Shoe Rooftop 5/14' noted and crossed
7.0Floor Heating · Vendor · Floor heating material + installation · 4/20/2026 · DONE · HIGH · 'Ordered 4/20/26 Completed' written in RED
8.0Master His-Her · Door Vendor Drywall · Drywall — all phases (ceiling, walls, hanging, finish) · 4/20-4/27 · DONE · HIGH · All four drywall items checked off on board
9.0Main Stair · APM / Metal Fab · Markup meeting — Thursday 5/14 · 5/14/2026 · DONE · HIGH · 'Markup Thursday 5/14' with checkmark on board
10.0Exterior Stone · CM · Liability insurance concluded · 4/29/2026 · DONE · HIGH · 'CM Done' crossed out in red — confirmed closed
11.0Water Meter · APM (reassigned from CM) · Water meter task — REASSIGNED to APM / Teco Gas · TBD · REASSIGNED · HIGH · 'CM Task' CROSSED OUT in red. 'APM Task' written. Teco Gas noted.
12.0FENCE · Facade Lead / Fab Lead · FENCE VE — 'Cluster F*ck — Facade Lead' written in RED · ASAP · Open — Escalating · CRITICAL · RED NEW: Site Super flagging coordination breakdown between Facade Lead and Fab Lead on fencing VE revision.
13.0PVC 24in Storm Drain · PM · 'Its been 4 months — Please lets get this scheduled' — red urgent note · ASAP · Open — Overdue · CRITICAL · RED NEW urgent escalation from Site Super. 4 months since last cleaning. PM to schedule immediately.
14.0HVAC · HVAC sub · Plenum HOT + PM Dates? — STILL on board, no resolution · ASAP · Open — No dates · CRITICAL · RED Still 'HOT' and 'PM Dates?' — unchanged from prior boards despite OAC flags.
15.0Metal Fabricator · the metal fabricator · Final Brake Metal — White Facade? (new red item) · ASAP · Open · CRITICAL · RED NEW on board. Facade brake metal color/finish decision still blocking fabrication.
16.0Metal Fabricator · the metal fabricator · Laundry Holding Tank Stands (new red item) · ASAP · Open · CRITICAL · RED NEW item not previously in any tracker. Laundry area holding tank stands required.
17.0HVAC · HVAC sub / Mech Eng · ISOLATORS — added to HVAC card · ASAP · Open · HIGH · NEW: 'ISOLATORS' written on HVAC card. Roof HVAC isolator engineering pending.
18.0Wine Cellar · Vendor TBD · Wine cellar delivery dates — 5/10 and 7/1/26 on board · 5/10 / 7/1/26 · Open · HIGH · NEW: Two dates added — 5/10 and 7/1/26. Phased or two separate deliveries?
19.0Gas Meter · Teco Gas / APM · Gas meter — APM Task + Teco Gas contact noted · TBD · Open · HIGH · NEW: 'APM Task' and 'Teco Gas' written on board. Installation date, permit, material needed.
20.0Pile Schedule · Pile Contractor · Pile inspection — MAY 11 date + Installation noted · 5/11/2026 · Scheduled · HIGH · NEW: 'Inspection Date MAY 11' and 'Installation' on board. Gas revision cleared this.
21.0Master His-Her · Tile Sub Stone Int. · Stone delivery date + metal strips. Process: material/layout/cut/install · TBD · Open · CRITICAL · No change — 'Date Starting?' still on board
22.0Master His-Her · Paint Sub · Paint — no owner approvals · TBD · Open · CRITICAL · No change — 'No Approvals' still on board. Interior priming week of 5/18 approved.
23.0Fence · MEP Eng / Fab Lead · Final revision, fabrication, installation dates · TBD · Open · CRITICAL · 'Cluster F*ck — Facade Lead' — see RED item above
24.0Main Stair · ELD / Metal Fab · Final revision, fabrication, installation dates · TBD · Open · HIGH · Markup done 5/14. Dates still TBD.
25.0Paver · Paving Sub · Order material, permit, install date, concrete driveway proposal · TBD · Open · HIGH · No change
26.0Landscaping · Landscape Arch / LAND · Completion plans date, permit, site selection · TBD · Open · HIGH · Landscape Arch on site 5/7. Tree conflict with utilities per OAC3 — walk needed.
27.0Civil · Civil Eng · Civil revision in progress — received site plan + city comments · 5/20/2026 · In Progress · HIGH · Civil Eng working per OAC3. Follow up 5/20.
28.0Slab · Concrete Sub · Starting date + rebar loop straps + completion · TBD · Open · CRITICAL · No change — follows pile inspection 5/11
29.0Cladding Vendor Cladding · Vendor · First order, cladding not including front door, job site delivery · TBD · Open · HIGH · No change
30.0Cladding Vendor Front Door · Vendor · Delivery date · TBD · Open · HIGH · No change
31.0Pool · Pool Sub · Pending revisions? Equipment install? Water feature relocate? · TBD · Open · HIGH · Pool contractor job walk 5/15 per OAC3
32.0T-G Wood Ceiling · Ceiling Sub · Paint Riglet White + T&G kitchen active · 4/21 · In Progress · MED · Ceiling Sub 3 workers daily on T&G kitchen per manpower log
33.0Windows · the window vendor — Window Vendor rep · Installation date (Sill Ricer proposal done) · TBD · Open · HIGH · Proposal crossed out = resolved. Install date TBD. Note: not to extend up 3/4in
34.0Propane Tank · Surveyor / Vendor · Plans printed big + survey · TBD · Open · MED · No change
35.0Electrical (site) · ELD · Relocate temp power date? · TBD · Open · HIGH · No change
36.0Back Fill · Site Contractor · Date confirmation · TBD · Open · MED · Follows slab
37.0Foam Paneling · SPS — Interiors rep · Installation completion · 5/31/2026 · Scheduled · MED · Delivery crossed out (done). Completion 5/31 circled.
38.0AV · AV VENDOR · Dressing room shade wire, alarm boxes, steam room speaker · TBD · Open · MED · No change
39.0Metal Fab · the metal fabricator · AC filter frame patio — completed? Friday check · 5/15/2026 · Open · HIGH · 'Patio completed? Friday' still on board
40.0Site Super · Site Super · Daily 11am + new red annotations (Interiors Co. coordination dates?) · Daily · Ongoing · HIGH · New red annotations visible in Site Super's column

▶ BOARD LOG | Prior (4/24)

🟢 = Completed/Crossed out on board | 🆕 = New info | 🔴 = Red ink on board (critical) | ⚠ = Trouble/Escalation
#Trade / Area · Sub / Vendor · Action Item · Target Date · Status · Priority · Board Update (latest photo)
1.0Elevator · Elevator Sub · Shaft painted + permit · 4/18/2026 · ✅ DONE · HIGH · ✅ Board confirmed complete
2.0Master His & Her · Door Vendor Drywall · Drywall ceiling hang · Mon 4/20 · ✅ DONE · HIGH · ✅ CROSSED OUT on board — completed
3.0Master His & Her · Door Vendor Drywall · Drywall wall hang · Mon 4/20 · ✅ DONE · HIGH · ✅ CROSSED OUT on board — completed
4.0Master His & Her · Door Vendor Drywall · Drywall hanging (3 days) · 4/23 · ✅ DONE · HIGH · ✅ CROSSED OUT on board
5.0AV / HVAC · HVAC Contractor · Condensate scope — HVAC owns · Resolved · ✅ DONE · HIGH · ✅ Resolved — HVAC Contractor confirmed
6.0Entrance / Main Stair · ELD Electric · ELD electrical start · 4/28/2026 · ✅ DONE · HIGH · 🆕 Date confirmed: ELD started 4/28
7.0Entrance / Main Stair · ELD Metal Fab · ELD metal fabricator start · 4/27/2026 · ✅ DONE · HIGH · 🆕 Date confirmed: started 4/27
8.0Master His & Her · Vendor TBD · Floor heating — material ordered · 4/21/2026 · ✅ DONE · HIGH · 🆕 'Material Ordered 4/21/26' on board
9.0HVAC · HVAC Lead (HVAC Sub) · ⚠ Supply duct failure at plenums — demand letter required · IMMEDIATE · Open — Escalating · 🔴 CRITICAL · 🔴 NEW from Site Super task list. Ducts coming apart. Demand letter to HVAC Lead. Escalate to the engineer if no response.
10.0Gas / Life Safety · PM / Engineer · ⚠ Gas revision — walls cannot close until complete · IMMEDIATE · Open — Life Safety Hold · 🔴 CRITICAL · 🔴 NEW life safety item. Cannot close any walls. Required for final sign-off.
11.0Gas / Electrical · the vendor (Electric) · ⚠ Underground electrical conflict with gas lines — CO pending · ~3 weeks · Pending CO · 🔴 CRITICAL · 🔴 NEW. CO from the vendor ~3 weeks. Must be approved before relocation can proceed.
12.0Master His & Her · Tile Sub Stone / Stone Sub AFS · His & Hers stone — delivery schedule to fabricator · ASAP · Open — No dates · 🔴 CRITICAL · 🔴 Backing date + vanity L-angles still red on board. Tile Sub process: Material→Layout→Cut→Install
13.0Electrical — 1st Floor · ELD / the metal fabricator · First floor electrical completion — date required · ASAP · Open · 🔴 CRITICAL · 🆕 ELD started 4/28. Completion date still needed. Revised lighting + relocations included.
14.0Front Facade · Foam Panel Sub · Fluted foam panels — stone vs. painted DECISION NEEDED · IMMEDIATE · Open — Owner Decision · 🔴 CRITICAL · 🔴 NEW. Panels being installed NOW. Must confirm finish immediately or work stops.
15.0HVAC — Master Wing · HVAC Sub · Final decision + owner approval for master wing HVAC · ASAP · Open · 🟠 HIGH · 🆕 Plenum still flagged 'Hot' + 'PM Dates?' on board. Master hallway + gym.
16.0Exterior Wood Ceiling · Sub TBD · Paint Riglet White · 4/21 · Open · HIGH · Riglets powder coating Wednesday per task list
17.0Pool Equipment · Pool Sub · Release pool equipment to sub — start work · ASAP · Open · 🟠 HIGH · 🆕 Pool pedestals + deck shop dwgs + fire pit shop dwgs all pending
18.0Transformer / Marina · Utility / Marina · Finalize pedestals + relocation · TBD · Open · 🟠 HIGH · 🆕 NEW from task list
19.0Steam Room · AV VENDOR · Finalize lighting + confirm with ownership · TBD · Open · 🟠 HIGH · Coordinate with AV VENDOR speaker install
20.0Garage Doors · Vendor TBD · Release for production · ASAP · Open · 🟠 HIGH · 🆕 NEW from task list — ready to release
21.0Spiral Stair & Railings · Metal Fab / TBD · Release scope + begin coordination + install · TBD · Open · 🟠 HIGH · 🆕 NEW from task list. Coordinate with the metal fabricator.
22.0Metal Fabricator · the metal fabricator · LED metal strip — galvanize (DEADLINE 4/29) · 4/29/2026 · Open — URGENT · 🔴 CRITICAL · 🔴 DEADLINE TODAY per task list. Approved on site.
23.0Metal Fabricator · the metal fabricator · Riglets T&G — powder coating · Wednesday · Open · 🟠 HIGH · 🆕 Due Wednesday
24.0Roof · Metal Fab / Roofing · Metal equipment enclosure — shop dwgs → fab → install · TBD · Open · 🟠 HIGH · 🆕 NEW from task list
25.0Garage · HVAC Sub · Garage A/C relocation — update plans · TBD · Open · 🟠 HIGH · 🆕 NEW from task list
26.0Retaining Wall · Civil / Public Works · Finalize retaining wall solution · TBD · Open · 🟠 HIGH · 🆕 NEW from task list
27.0Pavers / Driveways · Paving Sub · Finalize + start · TBD · Open · 🟠 HIGH · 🆕 NEW from task list
28.0Civil · Civil Engineer · French drain relocation · Thursday 4/30 · Scheduled · 🟠 HIGH · 🆕 Scheduled Thursday per task list — check required
29.0Civil · City / Plumber · Pipe work (City) — clean pipe, no lining · TBD · Open · 🟠 HIGH · 🆕 NEW from task list
30.0Propane · Vendor / Surveyor · Gas tank coordination + survey · TBD · Open · MED · After scaffolding removed
31.0Propane Tank Delivery · Vendor · Delivery date confirmation · TBD · Open · MED · No change
32.0Slab · Concrete Sub · Start date + rebar loop straps + completion · TBD · Open · 🔴 CRITICAL · Still TBD — feeds drywall + framing inspection
33.0Pile Schedule · Pile Contractor · Inspection + 10-day mobilization lead · TBD · Open · 🔴 CRITICAL · Must precede slab start
34.0Electrical (Site) · Electrician · Relocate temp power · TBD · Open · HIGH · Unchanged
35.0Back Fill · Site Contractor · Date confirmation · TBD · Open · MED · Follows slab
36.0Interior Painting · Paint Sub · Revise + resend proposal · ASAP · Open · 🟠 HIGH · 🆕 From task list. Paint approvals from owner still 'No Approvals' — escalate simultaneously.
37.0Exterior Painting · Paint Sub · New proposal — 25% darker color · ASAP · Open · 🟠 HIGH · 🆕 NEW. Owner wants 25% darker. Confirm color selection first.
38.0AV · PM / AV Sub · AV Change Order — confirm + process · TBD · Open · 🟠 HIGH · Still flagged on board
39.0Stucco · the stucco sub · PM's proposal to Stucco Sub · TBD · Open · 🟠 HIGH · Stucco started 4/21 — confirm proposal sent
40.0Windows · the window vendor — Window Vendor rep · Sill Ricer proposal + install date · TBD · Open · 🟠 HIGH · No change
41.0Finish Flooring · AnBos Corp · Sill Ricer proposal + install date · TBD · Open · MED · No change
42.0Architect · Facade Lead — AOR · Specialty Outlets proposal + NWF owner contact · TBD · Open · MED · No change
43.0Foam Paneling · SPS — Interiors rep · Installation completion · 5/31/2026 · Scheduled · MED · Delivery 4/27, start 4/27, complete 5/31
44.0Millwork Co. · vendor contact · Date — June 2026 timeframe · June 2026 · Open · MED · Contact: Millwork Co. rep
45.0Master His & Her · Paint Sub · Paint — master suites (NO OWNER APPROVALS) · TBD · Open — Blocked · 🔴 CRITICAL · 🔴 Red on board: 'No Approvals' from owner. Blocks all painting. Escalate immediately.
46.0Master His & Her · AV Vendor (unconfirmed) · Electrical fixtures — AV Vendor PROBABLY (not confirmed) · TBD · Open — Unassigned · 🟠 HIGH · 🔴 'AV Vendor Probably' — sub not confirmed. Must assign formally.
47.0Plumbing — Scope Q · Plumbing sub / HVAC · Who insulates condensing lines? Horizontal = TBD · ASAP · Open — Scope Gap · 🔴 CRITICAL · 🔴 'PM?' on board. Vertical=HVAC confirmed. Horizontal unassigned. Fails inspection if unresolved.
48.0AV VENDOR · AV VENDOR · Shade wire (dressing room) + alarm boxes + steam room speaker · TBD · Open · MED · No change
49.0Turntable · turntable vendor / installer · Proposal to Owner Rep — the installer to install metal guide · TBD · Open · MED · No change
50.0Site Super — Coverage · PM / APM (lead PM) · Daily 11AM field check-in (Site Super in recovery) · Daily · Ongoing · 🔴 CRITICAL · New lead PM onboarded